<font size=3>'''Typical diversion methods for working in the dry and their applicability'''.</font size><br>
+
<font size=3>'''Typical temporary stream crossing methods and their applicability'''.</font size><br>
Link to this [[Typical diversion methods for working in the dry and their applicability|table]]
+
Link to this [[Typical temporary stream crossing methods and their applicability|table]]
  
 
<table class="sortable">
 
<table class="sortable">
Line 15: Line 15:
 
*Generally most appropriate for streams with high flow velocities or steep gradients
 
*Generally most appropriate for streams with high flow velocities or steep gradients
 
</td>
 
</td>
<td>Use in large channels may require pier(s) or other supports, which increase disturbance to stream (see [https://stormwater.pca.state.mn.us/index.php?title=Construction_stormwater_practices_-_temporary_stream_crossing#Construction_recommendations_and_specifications Construction recommendations and specifications]).</td>
+
<td>Use in large channels may require pier(s) or other supports, which increase disturbance to stream (see [https://stormwater.pca.state.mn.us/index.php?title=Construction_stormwater_practices_-_temporary_stream_crossing#Construction_recommendations_and_specifications Construction recommendations and specifications])</td>
 
</tr>
 
</tr>
 
<tr>
 
<tr>
Line 22: Line 22:
 
*Most common temporary stream crossing
 
*Most common temporary stream crossing
 
*Most appropriate for short-term use
 
*Most appropriate for short-term use
*Generally appropriate for perennial or intermittent streams
+
*Generally appropriate for perennial or <span title="a well-defined channel that contains. water for only part of the year, typically during winter and spring when the aquatic."> '''intermittent streams'''</span>
 
*Generally preferred over fords as disturbance to stream is limited to construction and removal
 
*Generally preferred over fords as disturbance to stream is limited to construction and removal
 
</td>
 
</td>
Line 29: Line 29:
 
*Causes greatest obstruction to flow
 
*Causes greatest obstruction to flow
 
*May damage channel cross-section; culvert crossings should be planned to limit the number of crossings needed
 
*May damage channel cross-section; culvert crossings should be planned to limit the number of crossings needed
*Not appropriate for streams that are vertically degraded or incised
+
*Not appropriate for streams that are vertically degraded or <span title="A stream channel in which the bed has dropped and as a result, the stream is disconnected from its floodplain. Incised channels are often referred to as degraded channels."> '''incised'''</span>
 
</td>
 
</td>
 
</tr>
 
</tr>
Line 35: Line 35:
 
<td>Temporary ford (drive-through)</td>
 
<td>Temporary ford (drive-through)</td>
 
<td>
 
<td>
*Most appropriate for short-term use.
+
*Most appropriate for short-term use
*Generally appropriate for ephemeral or low flow perennial streams.
+
*Generally appropriate for <span title="a stream that flows only briefly during and following a period of rainfall in the immediate locality."> '''ephemeral'''</span> or low flow perennial streams
*Used when bridge or culvert crossings are not feasible; typically very shallow streams where stream banks are less than 4 feet above the stream invert.
+
*Used when bridge or culvert crossings are not feasible; typically very shallow streams where stream banks are less than 4 feet above the stream invert
 
</td>
 
</td>
 
<td>
 
<td>
*Use should be limited to dry season.
+
*Use should be limited to dry season
*Use should be limited to streams whose beds are armored.
+
*Use should be limited to streams whose beds are armored
 
*May degrade water quality due to contact with construction vehicles and equipment
 
*May degrade water quality due to contact with construction vehicles and equipment
 
</td>
 
</td>
Line 48: Line 48:
  
 
<noinclude>
 
<noinclude>
[[category:table]]
+
[[Category:Level 3 - General information, reference, tables, images, and archives/Tables/Erosion prevention]]
 
</noinclude>
 
</noinclude>

Latest revision as of 15:01, 24 July 2022

Typical temporary stream crossing methods and their applicability.
Link to this table

Stream crossing type Applicability Limitations
Temporary bridge
  • Results in least disturbance to stream bed and banks compared to other stream crossing methods
  • Typically no time of year restrictions for use
  • Generally most appropriate for streams with high flow velocities or steep gradients
Use in large channels may require pier(s) or other supports, which increase disturbance to stream (see Construction recommendations and specifications)
Temporary culvert (pipe)
  • Most common temporary stream crossing
  • Most appropriate for short-term use
  • Generally appropriate for perennial or intermittent streams
  • Generally preferred over fords as disturbance to stream is limited to construction and removal
  • May not be appropriate for large streams or during high flow conditions
  • Causes greatest obstruction to flow
  • May damage channel cross-section; culvert crossings should be planned to limit the number of crossings needed
  • Not appropriate for streams that are vertically degraded or incised
Temporary ford (drive-through)
  • Most appropriate for short-term use
  • Generally appropriate for ephemeral or low flow perennial streams
  • Used when bridge or culvert crossings are not feasible; typically very shallow streams where stream banks are less than 4 feet above the stream invert
  • Use should be limited to dry season
  • Use should be limited to streams whose beds are armored
  • May degrade water quality due to contact with construction vehicles and equipment