Unit costs related to diversion and working in the dry
Link to this table

Bid Item Item Description Units Average Price
2105601/00045 Temporary stream diversion system lump sum $27,523.34
2452601/00011 Steel sheet piling (temporary) lump sum $31,747.97
2452618/00011 Steel sheet piling (temporary) square foot $37.64