+ | = This is a test of the checklist format = | ||
+ | |||
+ | == BIORETENTION - Construction Inspection Checklist == | ||
+ | |||
+ | <table border="1"> | ||
+ | <tr> | ||
+ | <td width="800">Project: </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td>Location: </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td>Site Status: </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td>Date: </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td>Time: </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td>Inspector: </td> | ||
+ | </tr> | ||
+ | </table> | ||
+ | <br> | ||
+ | <table border="1"> | ||
+ | <tr> | ||
+ | <th width="200">Construction Sequence</th> | ||
+ | <th>Satisfactory/ Unsatisfacroty</th> | ||
+ | <th width="400">Comments</th> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td bgcolor="D0D0D0" colspan="3">1. Pre Construction</td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">Pre Construction Meeting</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">Runoff diverted</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">Facility area cleared</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">Soil tested for permibility</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">Project benchmark near site</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">facility location staked out</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">Temporary erosion and sedimant protection properly installed</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td bgcolor="D0D0D0" colspan="3">2. Excavation</td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">lateral slopes completly level</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">Soils not compacted durring excavation</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">Longitudinal slopes within design range</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | <tr> | ||
+ | <td width="200">Stockpile location not adjacent to excavation area and stablized with vegitation and/or silt fence</td> | ||
+ | <td>- </td> | ||
+ | <td>- </td> | ||
+ | </tr> | ||
+ | </table> |
PSH Operation | Polluting Activity |
---|---|
Vehicle Operations |
|
Outdoor Materials |
|
Waste Management |
|
Physical Plant Maintenance |
|
Turf and Landscaping |
|
Unique PSH Operations (Pools, Golf Courses, Marinas, Construciton, Restaurants, Hobby Famrs) |
Varies but includes:
|
Image Example | 200px |
Empty Circle | |
Quarter Circle | |
Half Circle | |
Full Circle |
Project: |
Location: |
Site Status: |
Date: |
Time: |
Inspector: |
Construction Sequence | Satisfactory/ Unsatisfacroty | Comments |
---|---|---|
1. Pre Construction | ||
Pre Construction Meeting | - | - |
Runoff diverted | - | - |
Facility area cleared | - | - |
Soil tested for permibility | - | - |
Project benchmark near site | - | - |
facility location staked out | - | - |
Temporary erosion and sedimant protection properly installed | - | - |
2. Excavation | ||
lateral slopes completly level | - | - |
Soils not compacted durring excavation | - | - |
Longitudinal slopes within design range | - | - |
Stockpile location not adjacent to excavation area and stablized with vegitation and/or silt fence | - | - |