m |
m (→Related pages) |
||
(3 intermediate revisions by the same user not shown) | |||
Line 77: | Line 77: | ||
*The underground infiltration is properly maintained (link). The performance of the underground infiltration should be regularly assessed (link). | *The underground infiltration is properly maintained (link). The performance of the underground infiltration should be regularly assessed (link). | ||
− | ==Underground infiltration example | + | ==Underground infiltration example== |
[[file:Schematic used for underground infiltration example.png|300px|left|thumb|alt=schematic used for example|<font size=3>Schematic used for the MIDS Calculator example for underground infiltration BMP. This example has 1.4 acres of impervious parking lot draining to an underground practice. Total pervious surface is 0.8 acres and includes the Turf Area and the area above the practice. See Step 1.</font size>]] | [[file:Schematic used for underground infiltration example.png|300px|left|thumb|alt=schematic used for example|<font size=3>Schematic used for the MIDS Calculator example for underground infiltration BMP. This example has 1.4 acres of impervious parking lot draining to an underground practice. Total pervious surface is 0.8 acres and includes the Turf Area and the area above the practice. See Step 1.</font size>]] | ||
[[file:Excel spreadsheet for example.png|300px|thumb|alt=screenshot of calculations|<font size=3>Screenshot from Excel spreadsheet used to calculate values needed as inputs for the calculator. The two values needed are shown in orange and include the Engineered media surface area (A<sub>M</sub>) and the Pipe/storage device volume (V<sub>P</sub>). Click on image to enlarge.</font size>]] | [[file:Excel spreadsheet for example.png|300px|thumb|alt=screenshot of calculations|<font size=3>Screenshot from Excel spreadsheet used to calculate values needed as inputs for the calculator. The two values needed are shown in orange and include the Engineered media surface area (A<sub>M</sub>) and the Pipe/storage device volume (V<sub>P</sub>). Click on image to enlarge.</font size>]] | ||
[[file:Screenshot site information tab underground infiltration.png|300px|thumb|alt=screenshot site information tab|<font size=3>Screen shot of the Site Information tab for underground infiltration. In this example, the user has entered a ZIP code and acres of pervious and impervious surfaces. Note also the user must indicate whether or not the calculator is being used to determine compliance with the Construction Stormwater permit. See Step 2.</font size>]] | [[file:Screenshot site information tab underground infiltration.png|300px|thumb|alt=screenshot site information tab|<font size=3>Screen shot of the Site Information tab for underground infiltration. In this example, the user has entered a ZIP code and acres of pervious and impervious surfaces. Note also the user must indicate whether or not the calculator is being used to determine compliance with the Construction Stormwater permit. See Step 2.</font size>]] | ||
[[file:Screenshot schematic tab underground infiltration.png|300px|thumb|alt=screenshot of watershed tab|<font size=3>Screenshot of the Watershed tab for underground infiltration. The user has dragged the Underground infiltration icon onto the Schematic screen. See Step 3.</font size>]] | [[file:Screenshot schematic tab underground infiltration.png|300px|thumb|alt=screenshot of watershed tab|<font size=3>Screenshot of the Watershed tab for underground infiltration. The user has dragged the Underground infiltration icon onto the Schematic screen. See Step 3.</font size>]] | ||
+ | |||
+ | This example was completed using Version 3 of the Calculator. | ||
An underground infiltration practice is to be constructed in a watershed that contains a 1.4 acre parking lot surrounded by 0.8 acres of pervious area (the latter includes turf area and the area above the underground practice). All of the runoff from the watershed will be treated by the underground practice. The soils across the entire area have a unified soils classification of classification of GW (HSG type A soil). The underground practice utilizes two 75-foot long, 10-foot diameter circular pipes (half-pipes in practice) with 1.0 foot of engineered media below the pipes. The depth from the overflow pipe to the engineered media is 4 feet. The ''Engineered media surface area (A<sub>M</sub>)'' and the ''Pipe/storage device volume (V<sub>P</sub>)'' are needed to calculate the volume retention. These values can be calculated using an [https://stormwater.pca.state.mn.us/index.php?title=File:Underground_storage_volumes_1.xlsx Excel spreadsheet] developed for this application. A screen shot of that spreadsheet is shown to the right for this example. The media porosity for this example is assumed to be 0.35 cubic feet per cubic foot. Following the MPCA Construction Stormwater General Permit requirement, water in the practice must drawdown in a 48 hour time period. The following steps detail how this system would be set up in the MIDS Calculator. | An underground infiltration practice is to be constructed in a watershed that contains a 1.4 acre parking lot surrounded by 0.8 acres of pervious area (the latter includes turf area and the area above the underground practice). All of the runoff from the watershed will be treated by the underground practice. The soils across the entire area have a unified soils classification of classification of GW (HSG type A soil). The underground practice utilizes two 75-foot long, 10-foot diameter circular pipes (half-pipes in practice) with 1.0 foot of engineered media below the pipes. The depth from the overflow pipe to the engineered media is 4 feet. The ''Engineered media surface area (A<sub>M</sub>)'' and the ''Pipe/storage device volume (V<sub>P</sub>)'' are needed to calculate the volume retention. These values can be calculated using an [https://stormwater.pca.state.mn.us/index.php?title=File:Underground_storage_volumes_1.xlsx Excel spreadsheet] developed for this application. A screen shot of that spreadsheet is shown to the right for this example. The media porosity for this example is assumed to be 0.35 cubic feet per cubic foot. Following the MPCA Construction Stormwater General Permit requirement, water in the practice must drawdown in a 48 hour time period. The following steps detail how this system would be set up in the MIDS Calculator. | ||
Line 121: | Line 123: | ||
==Requirements== | ==Requirements== | ||
− | [[File: | + | [[File:3 foot separation b.png|thumb|300px|alt=image illustrating separation distance to bedrock or seasonal high water table|<font size=3>Measurement of depth from the bottom of the infiltration BMP to the seasonally high water table or bedrock. Note that there must be a minimum of 2 feet separation when soils beneath the BMP are ripped, with a total separation distance of 3 feet or more. Infiltration BMPs include any BMP that allows water to infiltrate into the underlying soil.</font size>]] |
{{alert|The following are requirements of the [http://www.pca.state.mn.us/index.php/water/water-types-and-programs/stormwater/construction-stormwater/index.html Minnesota Construction Stormwater General Permit]|alert-danger}} | {{alert|The following are requirements of the [http://www.pca.state.mn.us/index.php/water/water-types-and-programs/stormwater/construction-stormwater/index.html Minnesota Construction Stormwater General Permit]|alert-danger}} | ||
Line 169: | Line 171: | ||
*[[Requirements, recommendations and information for using infiltration basin/underground infiltration BMPs in the MIDS calculator]] | *[[Requirements, recommendations and information for using infiltration basin/underground infiltration BMPs in the MIDS calculator]] | ||
− | [[Category:MIDS | + | [[Category:Level 3 - Models and modeling/Specific models/MIDS Calculator]] |
− | [[Category: | + | [[Category:Level 3 - Best management practices/Structural practices/Infiltration (trench/basin)]] |
</noinclude> | </noinclude> |
For an underground infiltration system, all stormwater captured below the outflow pipe in the underground pipe/storage device or in the underlying engineered media by the BMP is infiltrated into the underlying soil between rain events. All pollutants in the infiltrated water are credited as being reduced. Pollutants in the stormwater that bypasses the best management practice (BMP), including pollutants in water discharged through the outflow pipe, are not reduced.
For underground infiltration systems, the user must input the following parameters to calculate the volume and pollutant load reductions associated with the BMP.
The following are requirements or recommendations for inputs into the MIDS calculator. If the following are not met, an error message will inform the user to change the input to meet the requirement.
\( DDT_{calc}=(D_O+D_M)/(I_R/ 12) \)
“Required treatment volume,” or the volume of stormwater runoff delivered to the BMP, equals the performance goal (1.1 inches or user-specified performance goal) times the impervious area draining to the BMP, plus any water routed to the BMP from an upstream BMP. This stormwater is delivered to the BMP instantaneously.
The volume reduction achieved by a BMP compares the capacity of the BMP to the required treatment volume. The “Volume reduction capacity of BMP” is calculated using BMP inputs provided by the user. For this BMP the volume reduction credit is equal to the amount of water that can be instantaneously captured by the BMP in the storage device and in the engineered media below the outflow. The capture volume (V) is therefore equal to the following
\( V= V_P+[A_M*n*D_M ] \)
The “Volume of retention provided by BMP” is the amount of volume credit the BMP provides toward the performance goal. This value is equal to the lesser of the “Volume reduction capacity of BMP” calculated using the above method or the “Required treatment volume”. This check makes sure that the BMP is not getting more credit than necessary to meet the performance goal. For example, if the BMP is oversized the user will only receive credit for the “Required treatment volume” routed to the BMP, which corresponds with meeting the performance goal for the site .
Pollutant load reductions are calculated on an annual basis. Therefore, the first step in calculating annual pollutant load reductions is converting the “Volume reduction capacity of BMP,” which is an instantaneous volume reduction, to an annual volume reduction percentage. This is accomplished through the use of performance curves developed from multiple modeling scenarios. The performance curves use the “Volume reduction capacity of BMP”, the infiltration rate of the underlying soils, the contributing watershed percent impervious area, and the size of the contributing watershed to calculate a percent annual volume reduction. While oversizing a BMP above the “Required treatment volume” will not provide additional credit towards the performance goal volume, it may provide additional pollutant reduction.
A 100 percent removal is credited for all pollutants associated with the reduced volume of stormwater since these pollutants are either attenuated within the media or pass into the underlying soil with infiltrating water. Pollutants in the stormwater that bypasses the BMP through overflow are not reduced. A schematic of the removal rates can be seen in the sidebar.
NOTE: The user can modify event mean concentrations (EMCs) on the Site Information tab in the calculator. Default concentrations are 54.5 milligrams per liter for total suspended solids (TSS) and 0.3 milligrams per liter for total phosphorus (particulate plus dissolved). The calculator will notify the user if the default is changed. Changing the default EMC will result in changes to the total pounds of pollutant reduced.
An underground infiltration BMP can be routed to any other BMP, except for a green roof, stormwater disconnection (impervious disconnection), and a swale side slope or any BMP that would cause stormwater to be rerouted back to the infiltration basin already in the stormwater runoff treatment sequence. All BMPs can be routed to the underground infiltration, except for a swale side slope.
The following general assumptions apply in calculating the credit for a underground infiltration system. If these assumptions are not followed, the volume and pollutant reduction credits cannot be applied.
This example was completed using Version 3 of the Calculator.
An underground infiltration practice is to be constructed in a watershed that contains a 1.4 acre parking lot surrounded by 0.8 acres of pervious area (the latter includes turf area and the area above the underground practice). All of the runoff from the watershed will be treated by the underground practice. The soils across the entire area have a unified soils classification of classification of GW (HSG type A soil). The underground practice utilizes two 75-foot long, 10-foot diameter circular pipes (half-pipes in practice) with 1.0 foot of engineered media below the pipes. The depth from the overflow pipe to the engineered media is 4 feet. The Engineered media surface area (AM) and the Pipe/storage device volume (VP) are needed to calculate the volume retention. These values can be calculated using an Excel spreadsheet developed for this application. A screen shot of that spreadsheet is shown to the right for this example. The media porosity for this example is assumed to be 0.35 cubic feet per cubic foot. Following the MPCA Construction Stormwater General Permit requirement, water in the practice must drawdown in a 48 hour time period. The following steps detail how this system would be set up in the MIDS Calculator.
Step 1: Determine the watershed characteristics of your entire site. For this example, we have a 2.2 acre site that includes 1.4 acres of impervious area and 0.8 acres of pervious area in type A soils. The pervious area includes the turf area and the area above the underground practice. The entire site drains into the underground practice.
Step 2: Fill in the site specific information into the Site Information tab. This includes entering a ZIP Code (55105 for this example) and the watershed information from Step 1. The Managed Turf area includes the turf area plus the area above the underground practice. ZIP code and impervious area must be filled in or an error message will be generated. The user must also indicate whether the calculator is being used for permit compliance. Other fields on this screen are optional.
Step 3: Go to the Schematic tab and drag and drop the Underground infiltration icon into the Schematic window.
Step 4: Open the BMP properties for underground infiltration by right clicking on the Underground infiltration icon and selecting Edit BMP Properties, or by double clicking on the Underground infiltration icon.
Step 5: If help is needed, click on the Minnesota Stormwater Manual Wiki link or the Help button to review input parameter specifications and calculations pertinent to Underground infiltration.
Step 6: Determine the watershed characteristics for the underground infiltration practice. For this example the entire site is draining to the practice. The watershed parameters therefore include a 2.2 acre site with 1.4 acres of impervious area and 0.8 acres of pervious turf area in type A soils. There is no routing/downstream BMP for this BMP. Fill in this BMP-specific watershed information in the Watershed tab (1.4 acres of Impervious Cover and 0.8 acres of Managed Turf in A soils).
Step 7: Click on the BMP Parameters tab and enter the BMP design parameters. This Underground infiltration example requires the following entries:
Step 8: Click on BMP Summary tab to view results for this BMP.
Step 9: Click on the OK button to exit the BMP Properties screen.
Step 10: Click on Results tab to see overall results for the site.
This page was last edited on 23 November 2022, at 19:11.