==When should I consider infiltration?== | ==When should I consider infiltration?== | ||
If an industrial site fails benchmark monitoring, treatment may be required. If site conditions are appropriate for infiltration, it is usually the preferred option for managing stormwater runoff. The following site conditions are conducive to infiltration. | If an industrial site fails benchmark monitoring, treatment may be required. If site conditions are appropriate for infiltration, it is usually the preferred option for managing stormwater runoff. The following site conditions are conducive to infiltration. | ||
− | *[[Glossary#H|Hydrologic Soil Group]] (HSG) soils A, B, and C. For more information | + | *[[Glossary#H|Hydrologic Soil Group]] (HSG) soils A, B, and C. For more information, see [https://stormwater.pca.state.mn.us/index.php?title=Design_infiltration_rates this table]. |
*A minimum distance of 3 feet from the bottom of the infiltration practice to bedrock. For more information, see the section on [https://stormwater.pca.state.mn.us/index.php?title=Shallow_soils_and_shallow_depth_to_bedrock shallow soil and shallow bedrock]. | *A minimum distance of 3 feet from the bottom of the infiltration practice to bedrock. For more information, see the section on [https://stormwater.pca.state.mn.us/index.php?title=Shallow_soils_and_shallow_depth_to_bedrock shallow soil and shallow bedrock]. | ||
*A minimum distance of 3 feet from the bottom of the infiltration practice to the seasonal high water table. For more information, see the section on [https://stormwater.pca.state.mn.us/index.php?title=Shallow_groundwater shallow groundwater]. | *A minimum distance of 3 feet from the bottom of the infiltration practice to the seasonal high water table. For more information, see the section on [https://stormwater.pca.state.mn.us/index.php?title=Shallow_groundwater shallow groundwater]. |
When feasible, infiltration of stormwater runoff is a preferred option for managing stormwater. Infiltration keeps water near its point of origin, helps reduce downstream flooding, may help replenish groundwater supplies, and can be an effective treatment practice. This page provides a discussion of infiltration at industrial stormwater sites, including BMP options and infiltration constraints.
If an industrial site fails benchmark monitoring, treatment may be required. If site conditions are appropriate for infiltration, it is usually the preferred option for managing stormwater runoff. The following site conditions are conducive to infiltration.
In addition to the above physical site conditions, pollutants in the stormwater runoff must also be considered. The following general conditions apply for pollutant retention in infiltration BMPs.
Some pollutant sources should not be infiltrated or may be prohibited from infiltration. These are discussed in greater detail in the section on infiltration prohibitions.
There are several options for infiltrating stormwater runoff. BMP options include the following:
These BMPs are discussed in greater detail in [https://stormwater.pca.state.mn.us/index.php?title=BMPs_for_stormwater_infiltration this section of the manual. This page includes links to pages discussing design, construction, operation and maintenance, and cost for these BMPs.
Additional information about these BMPs can be found in the following tables.
Other options for infiltrating stormwater include discharging stormwater to vegetated (e.g. turf) areas, including capturing stormwater and using it for irrigation. Water applied to these vegetated areas is applied under conditions that allow the water to infiltrate. For more information, see the sections on turf and stormwater and rainwater harvest and use.
There are several constraints and prohibitions on infiltration in the industrial stormwater permit. These are summarized below.
professional hydrogeologist, engineer, etc.) and a report filed with the SWPPP. If industrial stormwater ponds and infiltration devices are found to be a contributor to contaminant increase or movement, the Permittee shall submit a plan to the Agency that describes how the Permittee will be reducing contaminants, redesigning, relocating, or eliminating the industrial stormwater ponds and infiltration devices, as needed, to eliminate the contribution to contaminant problems. The plan shall be submitted to the Agency within one year of the Permittee’s authorization to discharge under this permit or if discovered after application, within one year of discovery. The plan shall be implemented as soon as approval is granted by the Agency. The plan may utilize the results of, but does not reduce or eliminate more stringent requirements that may be imposed by other Agency regulatory programs. If agreement with the Agency on an acceptable plan cannot be reached, the Permittee must seek an individual NPDES/SDS permit.
professional hydrogeologist, engineer, etc.) to ensure that the industrial stormwater pond or infiltration device does not present a significant risk to groundwater. Generally accepted practices are described in the applicable portions of the Minnesota Stormwater Manual. If the industrial stormwater ponds and infiltration devices present a risk, appropriate measures, such as sealing or removal of the industrial stormwater ponds or infiltration devices, shall be taken to minimize or eliminate the risk. Evaluations shall be documented with the SWPPP.