m
m
Line 156: Line 156:
 
===Underdrains ([http://www.dot.state.mn.us/pre-letting/spec/ MNDOT Specifications 3245, 3247, 3248, 3278])===
 
===Underdrains ([http://www.dot.state.mn.us/pre-letting/spec/ MNDOT Specifications 3245, 3247, 3248, 3278])===
 
{{:Infiltration design guideline - underdrains}}
 
{{:Infiltration design guideline - underdrains}}
 +
 +
===Rock===
 +
See [http://www.dot.state.mn.us/pre-letting/spec/2018/2018-spec-book-final.pdf#%5B%7B%22num%22%3A1011%2C%22gen%22%3A0%7D%2C%7B%22name%22%3A%22XYZ%22%7D%2C69%2C570%2C0%5D MNDOT Standard Specification 3601].
 +
 +
===Weir===
 +
See MNDOT Standard Specifications [http://www.dot.state.mn.us/pre-letting/spec/2018/2018-spec-book-final.pdf#%5B%7B%22num%22%3A517%2C%22gen%22%3A0%7D%2C%7B%22name%22%3A%22XYZ%22%7D%2C69%2C710%2C0%5D 2461], [http://www.dot.state.mn.us/pre-letting/spec/2018/2018-spec-book-final.pdf#%5B%7B%22num%22%3A747%2C%22gen%22%3A0%7D%2C%7B%22name%22%3A%22XYZ%22%7D%2C69%2C710%2C0%5D 2573], [http://www.dot.state.mn.us/pre-letting/spec/2018/2018-spec-book-final.pdf#%5B%7B%22num%22%3A817%2C%22gen%22%3A0%7D%2C%7B%22name%22%3A%22XYZ%22%7D%2C69%2C720%2C0%5D 3137], [http://www.dot.state.mn.us/pre-letting/spec/2018/2018-spec-book-final.pdf#%5B%7B%22num%22%3A884%2C%22gen%22%3A0%7D%2C%7B%22name%22%3A%22XYZ%22%7D%2C69%2C686%2C0%5D 3301], [http://www.dot.state.mn.us/pre-letting/spec/2018/2018-spec-book-final.pdf#%5B%7B%22num%22%3A988%2C%22gen%22%3A0%7D%2C%7B%22name%22%3A%22XYZ%22%7D%2C69%2C238%2C0%5D 3491], [http://www.dot.state.mn.us/pre-letting/spec/2018/2018-spec-book-final.pdf#%5B%7B%22num%22%3A1011%2C%22gen%22%3A0%7D%2C%7B%22name%22%3A%22XYZ%22%7D%2C69%2C570%2C0%5D 3601].
  
 
===Plants===
 
===Plants===

Revision as of 21:07, 27 March 2018

This site is currently undergoing revision. For more information, open this link.
This page is in development

This page provides a discussion of design elements and design steps for dry swales, which are often called grass swales. The following discussion includes dry swales used as filtration or infiltration practices, with the distinction being the presence of an underdrain for filtration practices.

Green Infrastructure: Dry swales can be an important tool for retention and detention of stormwater runoff. Depending on design and construction, swales may provide additional benefits, including cleaner air, carbon sequestration, improved biological habitat, and aesthetic value.

Contents

Terminology

The following terminology is used throughout this design page.

Warning: REQUIRED - Indicates design standards stipulated by the MPCA Construction General Permit (CGP) or other consistently applicable regulations

HIGHLY RECOMMENDED - Indicates design guidance that is extremely beneficial or necessary for proper functioning of the practice, but not specifically required by the MPCA CGP.

RECOMMENDED - Indicates design guidance that is helpful for practice performance but not critical to the design.

Details and CADD images

Use this link to access .pdf diagrams of CADD drawings. To see all filtration CADD images in a combined pdf, click here.

Major design elements - Physical feasibility initial check

Before deciding to use a dry swale practice for stormwater management, it is helpful to consider several items that bear on the feasibility of using such a device at a given location. This section describes considerations in making an initial judgment as to whether or not a dry swale is the appropriate BMP for the site.

Infiltration constraints

If a dry swale is being considered for infiltration, the following links provide additional information on specific constraints to infiltration (applicable to dry swales without an underdrain). The Construction Stormwater General Permit prohibits infiltration under certain conditions, which are summarized and discussed in detail at this link.

Contributing drainage area

The RECOMMENDED maximum drainage area is typically 5 acres. Dry swales can be designed to convey runoff from larger drainage areas. However, volume reduction, water quality function, and ability to meet the MPCA CGP requirements is diminished.

Site topography and slopes

Unless slope stability calculations demonstrate otherwise (for guidance on calculating slope stability, see [1], [2], [3]), it is HIGHLY RECOMMENDED that swales be located a minimum horizontal distance of 200 feet from down-gradient slopes greater than 20 percent, and that slopes in contributing drainage areas be limited to 15 percent.

Site location/minimum setback

schematic showing horizontal and vertical setback distances
Schematic showing some horizontal and vertical separation distances from an infiltration BMP. A separation distance may be required, such as with a drinking water well, or recommended, as with an underground tank. (Source: CDM Smith) Not to scale.

If the swale is constructed as an infiltration practice, the following table summarizes required and recommended minimum horizontal and vertical setback distances from an infiltration practice to an above-ground or underground structure. It will be necessary to consult local ordinances for further guidance on siting infiltration practices.

Warning: A minimum setback of 50 feet between a dry swale without an underdrain (infiltration practice) and a water supply well is REQUIRED by the Minnesota Department of Health Rule 4725.4350

.

Required and recommended minimum vertical and horizontal separation distances. This represents the minimum distance from the infiltration practice to the structure of concern. If the structure is above-ground, the distance is measured from the edge of the BMP to the structure. If the structure is underground, the vertical separation distance represents the distance from the point of infiltration through the bottom of the system to the structure, while the horizontal separation (often called setback) distance is the shortest distance from the edge of the system to the structure.
Link to this table

Structure Distance (feet) Requirement or recommendation Note(s)
Vertical Saturated soil 3 Requirement1
Bedrock 3 Requirement1
Horizontal Public supply well 100 for sensitive wells; 50 for others3 Requirement
Building/structure/property line2 10 Recommended
Surface water none unless local requirements exist If nearby stream is impaired for chloride, see [4]
Septic system 35 Recommended
Contaminated soil/groundwater No specific distance. Infiltration must not mobilize contaminants.
Slope 200 Recommended from toe of slope >= 20%
Karst 1000 up-gradient 100 down-gradient Requirement1 active karst

1 Required under the Construction Stormwater General Permit
2 Minimum with slopes directed away from the building
3If treating an average of 10,000 gallons per day; otherwise separation distance is 300 feet


Depth to groundwater and bedrock

schematic illustrating separation distance from bottom of infiltration BMP to water table or top of bedrock
Schematic illustrating separation distance from bottom of infiltration BMP to water table or top of bedrock. This diagram includes a modified subsoil zone in which the subsoil has been ripped to alleviate compaction.

A separation distance of at least 3 feet is REQUIRED under the MPCA CGP between the bottom elevation of infiltration swales and the elevation of the seasonally high water table. Shallow bedrock areas should be avoided for dry swales with a minimum separation distance of 3 feet.

A field soil properties investigation is HIGHLY RECOMMENDED.

Karst topography

It is HIGHLY RECOMMENDED that underdrains and an impermeable liner be used for dry swales with filter media in active karst terrain because infiltration is typically not allowed in karst areas.. Geotechnical investigations are HIGHLY RECOMMENDED in karst areas.

Wellhead protection areas

See stormwater and wellhead protection for guidance and recommendations for determining the appropriateness of infiltrating stormwater in a Drinking Water Supply Management Area (DWSMA). For more information on source water protection see Minnesota Department of Health.

Warning: Infiltration is prohibited in areas within a Drinking Water Supply Management Area (DWSMA) as defined in Minn. R. 4720.5100Minn. R. 4720.5100, subp. 13., unless allowed by a local unit of government with a current MS4 permit.

Soils hydrologic soil group mapping (see Design infiltration rates)

See NRCS Web Soil Survey for hydrologic soil descriptions for the swale location. A and B soils are potentially suitable for a dry swale without an underdrain (infiltration swale). C and D soils are potentially suitable for a dry swale with an underdrain (filtration practice). The maximum allowed field-measured infiltration rate shall not exceed 8.3 inches per hour for an infiltration swale.

Major design elements - Practice and site considerations

Several considerations are made in this section for the conceptual design of dry swales. Further design guidance and specifications are made in the following sections.

Conveyance

It is HIGHLY RECOMMENDED that the design provide non-erosive flow velocities within the swale and at the outlet point to reduce downstream erosion. During the 10-year or 25-year storm (depending on local drainage criteria), discharge velocity should be kept below 4 feet per second for established grassed channels. Erosion control matting or rock should be specified if higher velocities are expected. See Erosion prevention practices for more information on erosion prevention practices.

Pretreatment

Pretreatment prior to the dry swale such as vegetated filter strips or side slopes, small sedimentation basins, water quality inlets, or other pretreatment BMPs should be evaluated. If the dry swale is being used to meet the Construction Stormwater General Permit, pretreatment is required.

Warning: To prevent clogging of the infiltration or filtration system, the Permittee(s) must use a pretreatment device such as a vegetated filter strip, small sedimentation basin, or water quality inlet (e.g., grit chamber) to settle particulates before the stormwater discharges into the infiltration or filtration system.

Anticipated flow

Although local drainage criteria may require a certain frequency event be used in the design, it is HIGHLY RECOMMENDED that larger events be considered depending on the adjacent property and associated risks.

Grading

  • Slope of swale: The longitudinal slope of a dry swale may vary from 0.5 to 2 percent and will affect the selection of swale type. It is HIGHLY RECOMMENDED that the design engineer consider the expected watershed flow to be conveyed by the swale in making the preliminary determination of design type.
  • Swale bottom: It is HIGHLY RECOMMENDED that the swale bottom be no less than 3 feet wide and should be adjusted with the cross-sectional area to be able to contain the expected range of flows within the swale. See additional design information on the cross-sectional area under the Swale Depth section.
  • Side slopes: It is RECOMMENDED that the maximum side slopes within a swale do not exceed 3H:1V and be designed based on the relative stage-dependent flow driven cross-sectional area.
schematic of a swale
Hydraulic parameters of a channel section. Click on image to enlarge.
  • Swale depth: Swale depth (pooled water depth) will be estimated based on the relative stage-dependent flow driven cross-sectional area to keep the swale from over topping.

The schematic at the right illustrates hydraulic parameters of a channel section. The area (A) is given by

\( A = ((b + d/tan(θ))d \)

the wetted perimeter (P) is given by

\( P = b + 2 (d / sin(θ)) \)

the hydraulic radius (R) is given by

\( R = (bd sin(θ) + d^2 cos(θ)) / (b sin(θ) + 2d) \)

and the flow quantity is given by Manning's Formula for swale sizing

\( Q = vA = 1.49/n AR^{0.67} S^{0.5} \)

where

Q = Flow Quantity (ft3/sec),
v = Velocity (ft/sec),
n = manning’s coefficient,
S = Slope (ft/ft), and
the other dimensions are shown in the schematic to the right.
  • Infiltration and filtration considerations: The design engineer should review the results of the feasibility check to assist in the selection of swale type. An additional consideration includes watershed soil transport to the site. Watersheds with unstable soils or lack of vegetative cover (e.g., construction, farmland and highly impervious surfaces) can generate and transport excessive sediments to the swale that may affect both infiltration and filtration capacity. In these situations, pretreatment via sedimentation processes is REQUIRED. Another consideration is the level of compaction and structure of in-situ soils, when considering dry swales. Construction of developments and roads, for example, significantly alter the parent state of native soils and therefore their hydrologic soil classification should be downgraded for feasibility study purposes.

Filter media

Swales designed for filtration (i.e. swales that have an underdrain) typically have engineered media. The media is comprised of a combination of sand and organic material on top of a pea gravel bed that encases a perforated drain pipe. The media assists in the removal of fine particulate and dissolved pollutants, improving on the overall performance of swale systems. See design specifications for media. If the filtered water is eventually discharged to a receiving water impaired for phosphorus, the practice should be designed to minimize phosphorus loss.

Soils with high infiltration rates (A and B soils) typically do not utilize engineered media. Swales constructed on these soils are suitable for infiltration and underdrains are not needed.

Underdrains

Underdrains are used when drawdown requirements cannot be me (e.g. C and D soils) or when there are other constraints to infiltration (see constraints to infiltration). Underdrains are comprised of a perforated, PVC pipe laid within filter media to convey runoff to either a stable day-lit area, a second form of treatment, or the storm sewer. A solid-walled PVC section of piping should be connected to the perforated drain pipe with a “tee” junction piece and extended to the swale’s surface to serve as an inspection and cleanout access point. These observation/maintenance ports are spaced throughout the system. See specifications for underdrains.

Treatment

Stormwater treatment in dry swales varies by design. For swales designed as infiltration practices, pollutants are attenuated through settling of sediment and adsorption of pollutants on soil media. Pollutants not attenuated by these processes will infiltrate deeply into the vadose zone, where they may be adsorbed, undergo chemical change, or leach to groundwater.

For swales designed as filtration practices, pollutants are attenuated through settling of sediment and adsorption of pollutants. Engineered media, which typically has a relatively organic matter content, is effective in attenuating metals, most organics, and bacteria. Soluble pollutants, such as nitrate, dissolved phosphorus, and chloride, may be taken up by vegetation but will largely be captured by the underdrain and returned to the stormwater drainage system. Unless lined, some infiltration will occur below the underdrain in filtration systems.

The use of impermeable check dams or weirs can enhance treatment by increasing the volume of water retained and increasing the contact time between soil or media and runoff water.

Vegetation

Vegetation plays a crucial role in dry swale treatment capacity, flow attenuation and stabilization of the swale itself (i.e., erosion control). It is HIGHLY RECEOMMENDED that preference is given to robust native, non-clump forming grasses as the predominant plant type within the swale flow area. Care must also be taken to consider species selection in light of sun exposure duration/timing as well as soil moisture, ponding depth and ponding duration.

Landscaping

Swales can be effectively integrated into the site planning process and aesthetically designed as attractive green spaces planted with native vegetation. Because vegetation is fundamental to the performance and function of the swale, aesthetically chosen vegetation may only be possible on the surface of the swales.

Snow considerations

Considering management of snow, the following are recommended

  • Plan a plow path during design phase and tell snowplow operators where to push the snow. Plan trees around (not in) plow path, with a 16 foot minimum between trees.
  • Plan for snow storage (both temporary during construction and permanent). Don’t plow into dry swales routinely. Dry swales should be a last resort for snow storage (i.e. only for very large snow events as “emergency overflow”.
  • Snow storage could be, for example, a designed pretreatment area.

For more information and example photos, see the section on snow and ice management.

Safety

Swales do not pose any major safety hazards. Potential hazards could occur from the steep side slope and checks of the swales if they are close to pedestrian traffic or roadways with no shoulders.

Materials specification

Erosion control (MNDOT Standard Specifications 2575, 3861-3898)

The use of temporary erosion control materials is REQUIRED in the design and construction of all swale types to allow for the establishment of firmly-rooted, dense vegetative cover. The dry swale bottom and side slopes up to the 10 year event should use robust erosion control matting that can resist the expected shear stresses associated with channelized flows. The matting should have a minimum life expectancy of three years. Upper banks of the swale slope should be protected by either similar matting or a straw/coconut blend erosion control blanket. See MNDOT specifications for guidance on selection of erosion control products.

Filter media

Filter media used in dry swale designs should follow guidance on material specifications within the bioretention section of the MN Stormwater Manual.

Underdrains (MNDOT Specifications 3245, 3247, 3248, 3278)

excample schematics of filtration practices
Example filtration practices having underdrains: a) biofiltration; b) permeable pavement; c) sand filter. (Source: CDM Smith).

The following are RECOMMENDED for infiltration practices with underdrains.

  • The minimum pipe diameter is 4 inches.
  • Install 2 or more underdrains for each infiltration system in case one clogs. At a minimum provide one underdrain for every 1,000 square feet of surface area.
  • Include at least 2 observation/cleanouts for each underdrain, one at the upstream end and one at the downstream end. Cleanouts should be at least 4 inches diameter vertical non-perforated schedule 40 PVC pipe, and extend to the surface. Cap cleanouts with a watertight removable cap.
  • Construct underdrains with Schedule 40 or SDR 35 smooth wall PVC pipe.
  • Install underdrains with a minimum slope of 0.5 percent, particularly in hydrologic soil group D soils (Note: to utilize Manning’s equation the slope must be greater than 0).
  • Include a utility trace wire for all buried piping.
  • For underdrains that daylight on grade, include a marking stake and animal guard;
  • For each underdrain have an accessible knife gate valve on its outlet to allow the option of operating the system as either an infiltration system, filtration system, or both. The valve should enable the ability to make adjustments to the discharge flow so the sum of the infiltration rate plus the underdrain discharge rate equal a 48 hour drawdown time.
  • Perforations should be 3/8 inches. Use solid sections of non-perforated PVC piping and watertight joints wherever the underdrain system passes below berms, down steep slopes, makes a connection to a drainage structure, or daylights on grade.
  • Spacing of collection laterals should be less than 25 feet.
  • Underdrain pipes should have a minimum of 3 inches of washed #57 stone above and on each side of the pipe (stone is not required below the pipe). Above the stone, two inches of choking stone is needed to protect the underdrain from blockage.
  • Avoid filter fabric .
  • Pipe socks may be needed for underdrains imbedded in sand. If pipe socks are used, then use circular knit fabric.

The procedure to size underdrains is typically determined by the project engineer. An example for sizing underdrains is found in the North Carolina Department of Environment and Natural Resources Stormwater BMP Manual. Underdrain spacing can be calculated using the following spreadsheet, which utilizes the vanSchilfgaarde Equation. The spreadsheet includes an example calculation. File:Underdrain spacing calculation.xlsx

Rock

See MNDOT Standard Specification 3601.

Weir

See MNDOT Standard Specifications 2461, 2573, 3137, 3301, 3491, 3601.

Plants

Refer to the vegetation section of the manual for selection of Minnesota native plants to be used in swales. Care must be taken to specify plants for their position in the system (swale bottom, side slopes and buffer). Preference towards robust non-clump forming grasses or sedges should be given to the swale bottom that can withstand flow forces as well as provide adequate filtration functions. It is also important to understand draw-down time not only within the channel itself, but in either in-situ soils or the filter media as plants have variable tolerance to the depth and duration of inundation as well as soil moisture period. Lastly, care should be taken to understand sun exposure requirements of various plants to ensure a robust, dense establishment of vegetative cover.

Open vegetated swale materials specifications.
Link to this table

Parameter Specification Size Note Design application
Dry swale soil USCS; ML, SM, SC n/a soil with a higher percent organic content is preferred dry swale, step pool
Dry swale sand ASTM C-33 fine aggregate concrete sand 0.02” to 0.04” dry swale, step pool
Check dam (pressure treated) AWPA Standard C6 6” by 6” or 8” by 8” do not coat with creosote; embed at least 3’ into side slopes dry swale, wet swale, step pool
Check Dam (natural wood) Black Locust, Red Mulberry, Cedars, Catalpa, White Oak, Chestnut Oak, Black Walnut 6” to 12” diameter; notch as necessary do not use the following, as these species have a predisposition towards rot: Ash, Beech, Birch, Elm, Hackberry, Hemlock, Hickories, Maples, Red and Black Oak, Pines, Poplar, Spruce, Sweetgum, Willow dry swale, wet swale, step pool
Filter Strip sand/gravel pervious berm sand: per dry swale sand gravel; AASHTO M-43 sand: 0.02” to 0.04” gravel: 1/2” to 1” Mix with approximately 25% loam soil to support grass cover crop; see Bioretention planting soil notes for more detail dry swale, step pool
Pea gravel diaphragm and curtain drain ASTM D 448 varies (No. 6) or (1/8” to 3/8”) use clean bank-run gravel dry swale, step pool
Underdrain gravel per pre-cast manufacturer 1.5” to 3.5” dry swale, step pool
Underdrain ASTM D-1785 or AASHTO M-278 6” rigid Schedule 40 PVC 3/8” perf. @ 6” o.c.; 4 holes per row dry swale, step pool
Rip rap per local criteria size per requirements based on 10- year design flow dry swale, wet swale, step pool


Design procedure – design steps

It is important to acknowledge that each site has unique and defining features that require site-specific design and analysis. The guidance provided below is intended to provide the fundamentals for designing dry swale systems to meet regulatory requirements but is not intended to substitute engineering judgment regarding the validity and feasibility associated with site-specific implementation. Designers need to be familiar with the hydrologic and hydraulic engineering principles that are the foundation of the design and they should also enlist the expertise of qualified individuals in stormwater management and stream restoration plantings with respect to developing appropriate planting plans and habitat improvement features.

Step 1. Make a preliminary judgment - consider basic issues for initial suitability screening

Make a preliminary judgment as to whether site conditions are appropriate for the use of a dry swale, and identify its function (filtration or infiltration) in the overall treatment system.

A. Consider basic issues for initial suitability screening, including:

  • Site drainage area
  • Site topography and slopes
  • Soil types
  • Regional or local depth to ground water and bedrock
  • Bottom of facility to be at least three feet above the seasonably high water table
  • Site location/minimum setbacks
  • Presence of active karst

B. Determine how the swale will fit into the overall stormwater treatment system, including:

  • Decide whether the swale is the only BMP to be employed, or if are there other BMPs addressing some of the treatment requirements.
  • Decide where on the site the swale will most likely to be located.

Step 2. Confirm design criteria and applicability

A. Determine whether the swale must comply with the MPCA CGP. To determine if permit compliance is required, see Permit Coverage and Limitations.

B. Check with local officials, watershed organizations, and other agencies to determine if there are any additional restrictions and/or surface water or watershed requirements that may apply.

Step 3. Perform field verification of site suitability

image of MPD infiltrometer
The modified Philip-Dunne infiltrometer, as well as other direct infiltration measurements such as double ring infiltrometers, are preferred methods for measuring infiltration rates, compared to soil borings and pits. Image: University of Minnesota, St. Anthony Falls Laboratory.
Warning: The Construction Stormwater permit includes the following requirements.

16.10. Permittees must provide at least one soil boring, test pit or infiltrometer test in the location of the infiltration practice for determining infiltration rates.

16.11. For design purposes, permittees must divide field measured infiltration rates by 2 as a safety factor or permittees can use soil-boring results with the infiltration rate chart in the Minnesota Stormwater Manual to determine design infiltration rates. When soil borings indicate type A soils, permittees should perform field measurements to verify the rate is not above 8.3 inches per hour. This permit prohibits infiltration if the field measured infiltration rate is above 8.3 inches per hour.


Designers should evaluate soil properties during preliminary site layout with the intent of installing infiltration practices on soils with the highest infiltration rates ( hydrologic soil group A and B). Preliminary planning for the location of an infiltration device may be completed using a county soil survey or the NRCS Web Soil Survey. These publications provide HSG information for soils across Minnesota. To ensure long-term performance, however, field soil measurements are desired to provide site-specific data.

If the initial evaluation indicates that an infiltration practice would be a good BMP for the site, it is RECOMMENDED that soil borings or pits be dug within the proposed boundary of the infiltration practice to verify soil types and infiltration capacity characteristics and to determine the depth to groundwater and bedrock. Soil borings for building structural analysis are not acceptable. In all design scenarios, a minimum of one soil boring (two are recommended) shall be completed to a depth 5 feet below the bottom of the proposed infiltration Stormwater Control Measure (SCM or BMP) (Dakota County Soil and Water Conservation District, 2012) per ASTM D1586 (ASTM, 2011). For infiltration SCMs with surface area between 1000 and 5000 square feet, two borings shall be made. Between 5000 and 10000 square feet, three borings are needed, and for systems with greater than 10000 square feet in surface area, 4 or more borings are needed. For each additional 2500 square feet beyond 12,500 square feet, an additional soil boring should be made. Soil borings must be undertaken during the design phase (i.e. prior to the commencement of construction) to determine how extensive the soil testing will be during construction. Borings should be completed using continuous split spoon sampling, with blow counts being recorded to determine the level of compaction of the soil. Soil borings are needed to understand soil types, seasonally high groundwater table elevation, depth to karst, and bedrock elevations.

Recommended number of soil borings, pits or permeameter tests for bioretention design. Designers select one of these methods.
Link to this table

Surface area of stormwater control measure (BMP)(ft2) Borings Pits Permeameter tests
< 1000 1 1 5
1000 to 5000 2 2 10
5000 to 10000 3 3 15
>10000 41 41 202

1an additional soil boring or pit should be completed for each additional 2,500 ft2 above 12,500 ft2
2an additional five permeameter tests should be completed for each additional 5,000 ft2 above 15,000 ft2


It is HIGHLY RECOMMENDED that soil profile descriptions be recorded and include the following information for each soil horizon or layer (Source: Site Evaluation for Stormwater Infiltration, Wisconsin Department of Natural Resources Conservation Practice Standards 2004):

  • thickness, in inches or decimal feet;
  • Munsell soil color notation;
  • soil mottle or redoximorphic feature color, abundance, size and contrast;
  • USDA soil textural class with rock fragment modifiers;
  • soil structure, grade size and shape;
  • soil consistence, root abundance and size;
  • soil boundary; and
  • occurrence of saturated soil, impermeable layers/lenses, ground water, bedrock or disturbed soil.

It is RECOMMENDED that a standard soil boring form be used. A good example is File:Boring Pit Log form.docx. The NRCS Field Book for Describing and Sampling Soils provide detailed information for identifying soil characteristics. Munsell color charts can be found here.

Warning: A separation distance of 3 feet is REQUIRED between the bottom of the infiltration practice and the elevation of the seasonally high water table (saturated soil) or top of bedrock (i.e. there must be a minimum of 3 feet of undisturbed soil beneath the infiltration practice and the seasonally high water table or top of bedrock).

It is HIGHLY RECOMMENDED that the field verification be conducted by a qualified geotechnical professional.

Groundwater mounding, the process by which a mound of water forms on the water table as a result of recharge at the surface, can be a limiting factor in the design and performance of infiltration practices. A groundwater mounding analysis is RECOMMENDED to verify separation distances required for infiltration practices. For more information on groundwater mounding, see the following sections in this manual.

Step 4. Select design variant based on physical suitability evaluation

Once the physical suitability evaluation is complete, it is HIGHLY RECOMMENDED that the better site design principles be applied in sizing and locating the filtration practice(s) on the development site. Given the drainage area, select the appropriate swale practice for the first iteration of the design process. Note: Information collected during the physical suitability evaluation (see Step 1) should be used to explore the potential for multiple swale practices versus relying on a single facility.

Step 5. Compute runoff control volumes and other key design parameters

If the swale is being designed to meet the requirements of the MPCA Permit, the REQUIRED treatment volume is the water quality volume of 1 inch of runoff from the new impervious surfaces created from the project. If part of the overall Vwq is to be treated by other BMPs, subtract that portion from the Vwq to determine the part of the Vwq to be treated by the dry swale.

For swales, compute the following design parameters:

A. Calculate the maximum discharge loading per foot of swale width

\(q = (0.00236/n) · Y · 1.67 · S · 0.5 \)

Where:

q = discharge per foot of length of the swale, from Manning’s equation (cfs/ft);
Y = allowable depth of flow (inches);
S = slope of swale (percent) (0.5 to 2 percent); and
n = Manning’s “n” roughness coefficient (use 0.15 for short prairie grass, 0.25 for dense grasses such as bluegrass, buffalo grass, blue grama grass and other native grass mixtures).

B. Use a recommended hydrologic model to compute Qwq

C. Minimum swale length (in feet) = Qwq / q

Where:

Qwq = the water quality peak discharge (cubic feet per second)

Step 6. Compute number of check dams

  • Design to contain entire Vwq.
  • Channel slopes between 0.5 and 2 percent are recommended unless topography necessitates a steeper slope, in which case 6- to 12-inch drop structures can be placed to limit the energy slope to within the recommended 0.5 to 2 percent range. Energy dissipation will be required below the drops. Spacing between the drops should not be closer than 50 feet. Depth of the Vwq at the downstream end should not exceed 18 inches.

Step 7. Calculate drawdown time

Filtration swales (swales with an underdrain) include a bed consisting of a permeable soil layer at least 30 inches in depth, above a 6-inch diameter perforated PVC pipe (AASHTO M 252) longitudinal underdrain in a 12-inch gravel layer. The soil media should have an infiltration rate of at least 0.25 inches per hours with a maximum of 1.5 inches per hour and contain organic material to facilitate pollutant removal but not contribute to phosphorus leaching. A permeable filter fabric is placed between the gravel layer and the overlying soil. Dry swale channels are sized to store and filter the entire Vwq and allow for full filtering through the permeable soil layer.

Step 8. Check 2-year and 10-year velocity erosion potential and freeboard

Check for erosive velocities and modify design as appropriate based on local conveyance regulations. Provide a minimum of 6 inches of freeboard.

Step 9. Design low flow control at downstream headwalls and checkdams

Design control to pass Vwq in 48 hours.

Step 10. Design inlets, sediment forebay(s), and underdrain system

Inlets to swales must be provided with energy dissipaters such as riprap or geotextile reinforcement. Pretreatment of runoff is typically provided by a sediment forebay located at the inlet. Enhanced swale systems that receive direct concentrated runoff may have a 6-inch drop to a pea gravel diaphragm flow spreader at the upstream end of the control. A pea gravel diaphragm and gentle side slopes should be provided along the top of channels to provide pretreatment for lateral sheet flows. The underdrain system should discharge to the storm drainage infrastructure or a stable outfall.

Step 11. Check volume, peak discharge rates and drawdown time against state, local, and watershed organization requirements (NOTE: steps are iterative)

Follow the design procedures identified in the Unified Sizing Criteria section of the Manual to determine the volume control and peak discharge requirements for water quality, recharge (not required), channel protection, overbank flood and extreme storm.

Model the proposed development scenario using a surface water model appropriate for the hydrologic and hydraulic design considerations specific to the site. This includes defining the parameters of the swale practice defined above: ponding elevation and area (defines the ponding volume), infiltration rate and method of application (effective filtration area), and outlet structure and/or flow diversion information. The results of this analysis can be used to determine whether or not the proposed design meets the applicable requirements. If not, the design will have to be re-evaluated.

Warning: The following items are specifically REQUIRED by the MPCA Permit:

A. Volume: Swale systems shall be sufficient to infiltrate a water quality volume of 1 inch of runoff from the new impervious surfaces created by the project. If this criterion is not met, increase the storage volume of the practice or treat excess water quality volume (Vwq) in an upstream or downstream BMP (see Step 5). If this requirement cannot be met, infiltrate to the extent possible and ensure that the remaining volume is treated through filtration.
B. Drawdown: Dry swales shall discharge through the soil or filter media in 48 hours or less. Additional flows that cannot be infiltrated or filtered in 48 hours should be routed to bypass the system through a stabilized discharge point.

Experience has demonstrated that, although the drawdown period is 48 hours, there is often some residual water pooled in the infiltration practice after 48 hours. This residual water may be associated with reduced head, water gathered in depressions within the practice, water trapped by vegetation, and so on. The drawdown period is therefore defined as the time from the high water level in the practice to 1 to 2 inches above the bottom of the facility. This criterion was established to provide the following: wet-dry cycling between rainfall events; unsuitable mosquito breeding habitat; suitable habitat for vegetation; aerobic conditions; and storage for back-to-back precipitation events. This time period has also been called the period of inundation.

Step 12. Finalize the cross-section and profile design for the project

  • Grading plan: Develop a grading plan based on the preliminary profile and cross-section typical design.
  • Dimensions: Adjust the preliminary profile dimensions to accommodate site specific concerns/impacts. Minimum design parameters for hydraulic, water quality, and quantity management criteria should be rechecked based on adjustments to the dry swale to ensure that safe and adequate conveyance is still maintained.
  • Check dams: Adjust the preliminary check dam dimensions to accommodate site specific concerns/impacts. Minimum design parameters for hydraulic and water quality criteria should be rechecked based on adjustments to the check dams to ensure that safe and adequate conveyance is still maintained.
  • Site stabilization: Course woodchips and compost should be used throughout the limit of disturbance for site stabilization. All areas should be seeded and planted as well as blanketed/matted. Jute blanket should be used within the swale bottom and side slopes. Erosion control blanket with biodegradable netting should be used above the side slopes within the floodplain.
  • Excess materials: It is advisable that excess materials, i.e., cobbles and boulders, be placed at the edge of the cross-section for use during the maintenance phase to correct any physical instability.

Step 13. Prepare vegetation and landscaping plan

A landscaping plan for a swale should be prepared to indicate how the enhanced swale system will be stabilized and established with vegetation. Landscape design should specify proper species and be based on specific site, soils, sun exposure and hydric conditions present along the swale. Further information on plant selection and use can be found in the Minnesota plant lists section.

Step 14. Prepare operation and maintenance plan

See Operation and Maintenance section for guidance on preparing an O&M plan.

Step 15. Prepare cost estimate

See Cost Considerations section for guidance on preparing a cost estimate that includes both construction and maintenance costs.


Related pages