Below is a summary of requirements, recommendations and other information for using the Minimal Impacts Design Standards (MIDS) calculator for bioretention BMPs.

Warning: The following are requirements of the Minnesota Construction Stormwater General Permit
  • 3 foot separation from the bottom of the bioretention system to seasonal high water table
  • Use most restrictive infiltration rate within 3 feet of the bottom of the BMP
  • Drawdown time of 24 hours for trout streams
  • For measured infiltration rates, apply a safety factor of 2 (2.5 for permeable pavement)
  • Pretreatment


Caution: The following are recommendations for inputs into the MIDS calculator
  • 5 acre or less for contributing area
  • Maximum ponding depth of 18 inches, reduced to 6 inches if there is no site information (4 feet for infiltration basin)
  • Field tested infiltration rates over table values


Information: The following information may be useful in determining inputs for the MIDS calculator
  • Guidance on determining infiltration rates
  • Information on site constraints (shallow soil, karst, etc.)
  • Information on assessing BMPs
  • Information on design metrics (high flow bypass, ponding depths, drawn down)
  • Guidance on pretreatment
  • Information on soil mixes
  • Plant information, including species list that show water tolerance, potential effects of different species on infiltration rates, planting guidance
  • Construction specifications
  • Information on operation and maintenance of bioretention BMPs.