==Recommendations==
 
==Recommendations==
 
{{alert|The following are recommendations for inputs into the MIDS calculator|alert-warning}}
 
{{alert|The following are recommendations for inputs into the MIDS calculator|alert-warning}}
*5 acre or less for contributing area
+
*5 acres or less for contributing area
 
*Maximum ponding depth of 18 inches, reduced to 6 inches if there is no site information (4 feet for infiltration basin)
 
*Maximum ponding depth of 18 inches, reduced to 6 inches if there is no site information (4 feet for infiltration basin)
 
*Field tested infiltration rates over table values
 
*Field tested infiltration rates over table values

Revision as of 20:45, 16 May 2013

Below is a summary of requirements, recommendations and other information for using the Minimal Impacts Design Standards (MIDS) calculator for bioretention BMPs. Links to MIDS pages and the MIDS calculator are included at the bottom of this page.

Requirements

Warning: The following are requirements of the Minnesota Construction Stormwater General Permit
  • 3 foot separation from the bottom of the bioretention system to seasonal high water table
  • Use most restrictive infiltration rate within 3 feet of the bottom of the BMP
  • Drawdown time of 24 hours for trout streams
  • For measured infiltration rates, apply a safety factor of 2 (2.5 for permeable pavement)
  • Pretreatment


Recommendations

Caution: The following are recommendations for inputs into the MIDS calculator
  • 5 acres or less for contributing area
  • Maximum ponding depth of 18 inches, reduced to 6 inches if there is no site information (4 feet for infiltration basin)
  • Field tested infiltration rates over table values

Information

Information: The following information may be useful in determining inputs for the MIDS calculator