m (→Step 25) |
m |
||
Line 399: | Line 399: | ||
'''PREVIOUS STEP''': It was determined that shallow groundwater or shallow bedrock is present within 3 feet of the bottom of the BMP and the BMP cannot be relocated or raised in elevation to achieve a 3 foot or greater separation from bedrock or groundwater. | '''PREVIOUS STEP''': It was determined that shallow groundwater or shallow bedrock is present within 3 feet of the bottom of the BMP and the BMP cannot be relocated or raised in elevation to achieve a 3 foot or greater separation from bedrock or groundwater. | ||
− | |||
− | |||
==Step 32== | ==Step 32== | ||
Line 451: | Line 449: | ||
'''PREVIOUS STEP''': It was determined that contaminated soil, contaminated groundwater, or hotspot runoff is present on the site and cannot be isolated or mitigated. | '''PREVIOUS STEP''': It was determined that contaminated soil, contaminated groundwater, or hotspot runoff is present on the site and cannot be isolated or mitigated. | ||
− | |||
− | |||
==Step 36== | ==Step 36== | ||
Line 516: | Line 512: | ||
'''PREVIOUS STEP''': It was determined that soils on the site have an infiltration rate of less than 0.2 inches per hour, the BMP cannot be relocated to areas with a higher infiltration rate, and the BMP cannot be sized to drain within 48 hours (24 hours in locations that are tributary to trout streams) | '''PREVIOUS STEP''': It was determined that soils on the site have an infiltration rate of less than 0.2 inches per hour, the BMP cannot be relocated to areas with a higher infiltration rate, and the BMP cannot be sized to drain within 48 hours (24 hours in locations that are tributary to trout streams) | ||
− | |||
− | |||
==Step 42== | ==Step 42== | ||
Line 567: | Line 561: | ||
'''PREVIOUS QUESTION and ANSWER''': It was determined that soils on the site have an infiltration rate greater than 8 inches per hour, the BMP cannot be relocated to an area with an infiltration rate lower than 8 inches per hour, or the subgrade cannot be modified to slow the infiltration rate to less than 8 inches per hour | '''PREVIOUS QUESTION and ANSWER''': It was determined that soils on the site have an infiltration rate greater than 8 inches per hour, the BMP cannot be relocated to an area with an infiltration rate lower than 8 inches per hour, or the subgrade cannot be modified to slow the infiltration rate to less than 8 inches per hour | ||
− | |||
− | |||
==Step 46== | ==Step 46== | ||
Line 615: | Line 607: | ||
Provide the following information | Provide the following information | ||
*provide report documenting potential hydrologic impacts from infiltration on the site, prepared by a registered engineer, hydrologist, or wetland specialist | *provide report documenting potential hydrologic impacts from infiltration on the site, prepared by a registered engineer, hydrologist, or wetland specialist | ||
− | |||
− | |||
==Step 50== | ==Step 50== | ||
Line 632: | Line 622: | ||
*If Flexible Treatment Option 1 was determined based on presence of low infiltrating soils, provide soil boring or infiltration test results documenting low-infiltrating soils | *If Flexible Treatment Option 1 was determined based on presence of low infiltrating soils, provide soil boring or infiltration test results documenting low-infiltrating soils | ||
*if Flexible Treatment Option 1 was determined based on presence of adverse surface water hydrologic impacts from infiltration practices, provide a report that documents the potential hydrologic impacts from infiltration on the site, prepared by a registered engineer, hydrologist, or wetlands specialist. | *if Flexible Treatment Option 1 was determined based on presence of adverse surface water hydrologic impacts from infiltration practices, provide a report that documents the potential hydrologic impacts from infiltration on the site, prepared by a registered engineer, hydrologist, or wetlands specialist. | ||
− | |||
− | |||
==Step 51== | ==Step 51== | ||
Line 645: | Line 633: | ||
**0.55 inches of runoff from the new and fully reconstructed impervious surfaces | **0.55 inches of runoff from the new and fully reconstructed impervious surfaces | ||
**1.1 inches of runoff from the net increase in impervious area | **1.1 inches of runoff from the net increase in impervious area | ||
− | |||
− | |||
==Step 52== | ==Step 52== | ||
Line 723: | Line 709: | ||
'''PREVIOUS STEP''': It was determined that the site is located within a DWSMA, wellhead protection area or within 200 feet of a drinking water well and infiltration is not allowed by the LGU. | '''PREVIOUS STEP''': It was determined that the site is located within a DWSMA, wellhead protection area or within 200 feet of a drinking water well and infiltration is not allowed by the LGU. | ||
− | |||
− | |||
==Step 57== | ==Step 57== | ||
Line 838: | Line 822: | ||
**there are zoning and land use requirements that make the Performance Goal not feasible and BMP relocation is not feasible; or | **there are zoning and land use requirements that make the Performance Goal not feasible and BMP relocation is not feasible; or | ||
**there are existing or proposed structures or infrastructure that make the Performance Goal not feasible and BMP relocation is not feasible. | **there are existing or proposed structures or infrastructure that make the Performance Goal not feasible and BMP relocation is not feasible. | ||
− | |||
− | |||
==Step 65== | ==Step 65== | ||
Line 862: | Line 844: | ||
**there are zoning and land use requirements that make the Performance Goal not feasible and BMP relocation is not feasible; or | **there are zoning and land use requirements that make the Performance Goal not feasible and BMP relocation is not feasible; or | ||
**there are existing or proposed structures or infrastructure that make the Performance Goal not feasible and BMP relocation is not feasible. | **there are existing or proposed structures or infrastructure that make the Performance Goal not feasible and BMP relocation is not feasible. | ||
− | |||
− | |||
==Step 66== | ==Step 66== |
A flow chart was developed to determine the appropriate performance goal or Flexible Treatment Option for a new development, redevelopment, or linear site. You may access a pdf version of the flow chart (File:Final MIDS Flow chart.pdf) or follow the flow chart through the sequence of questions starting at Step 1 below. If you would like a copy of the flowchart in Visio, so that you can edit it, please contact us.
The wiki version of the flow chart, which starts below at Step 1, takes you through a series of questions and steps to ultimately arrive at a performance goal. The wiki version does not necessarily take you through each step nor does it completely match the pdf version of the flow chart. However, the sequence of questions and answers takes you to the same result.
Two advantages of using the wiki version on this page are that 1) the path through questions and answers is straightforward and 2) there are links, discussions, and images to assist you in answering questions.
Did you gather the site information necessary to proceed through the flow chart?
Prior to using the flow chart, gather the following preliminary information.
Does project create one acre or more of new and/or fully reconstructed impervious surfaces?
PREVIOUS QUESTION and ANSWER: The previous question defined the performance goals.
MIDS PERFORMANCE GOAL DOES NOT APPLY
The project creates less than 1 acre of impervious surface.
You have completed the flow chart.
Return to Minimal Impact Design Standards main page
Return to Design Sequence Flowchart-Flexible treatment options
Is the project linear?
PREVIOUS QUESTION and ANSWER: Does project create one acre or more of new and/or fully reconstructed impervious surfaces? Answer - Yes
Are there constraints due to lack of available ROW, off site drainage and/or rate control requirements?
Is Flexible Treatment Option (FTO) 2 feasible?
PREVIOUS QUESTION and ANSWER: Are there restraints due to lack of available right-of-way, off-site drainage, and/or rate control requirements? Answer: Yes
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the following information
PREVIOUS STEP: It was determined that the site is linear, there are constraints due to lack of right-of-way or off/site drainage and/or rate control requirements, and a reasonable effort to acquire all of the right-of-way cannot be made.
Off-site mitigation (including banking or cash or treatment on another project, as determined by the local authority) equivalent to the volume reduction performance goal can be used in areas selected in the following order of preference:
PREVIOUS QUESTION: It was determined that Flexible Treatment Option 2 is not feasible.
Are there zoning and land use requirements that make the Performance Goal not feasible?
PREVIOUS QUESTION and ANSWER:
or
Is BMP relocation feasible
PREVIOUS QUESTION and ANSWER: Are there zoning and land use requirements that make the Performance Goal not feasible? Answer: Yes
Is Flexible Treatment Option (FTO) 1 feasible?
PREVIOUS QUESTION and ANSWER: Is BMP relocation feasible - Answer: No
Applicant attempts to comply with the following conditions:
Is Flexible Treatment Option (FTO) 2 feasible?
Applicant attempts to comply with the following conditions:
PREVIOUS QUESTION and ANSWER: Is Flexible Treatment Option (FTO) 1 feasible? - Answer: No
Is the site located in a DWSMA (Drinking Water Supply Management Area), wellhead protection area, or within 200 feet of a drinking water well?
A drinking water supply management area (DWSMA) is the Minnesota Department of Health (MDH) approved surface and subsurface area surrounding a public water supply well that completely contains the scientifically calculated wellhead protection area and is managed by the entity identified in a wellhead protection plan. The boundaries of the drinking water supply management area are delineated by identifiable physical features, landmarks or political and administrative boundaries.
PREVIOUS QUESTION and ANSWER
or
Can a Local Government Unit (LGU) provide a higher level of engineering review to ensure a functioning system that prevents adverse impacts to groundwater?
PREVIOUS QUESTION and ANSWER: Is the site located in a DWSMA, Wellhead Protection Area, or within 200 feet of a drinking water well? - Answer: Yes
Are there existing or proposed structures or infrastructure (e.g. rate control BMPs, utilities, buildings, roadway, easements) that make the Performance Goal not feasible?
PREVIOUS QUESTION and ANSWER
or
Is BMP relocation feasible?
PREVIOUS QUESTION and ANSWER: - Are there existing or proposed structures or infrastructure (e.g. rate control BMPs, utilities, buildings, roadway, easements) that make the Performance Goal not feasible? - Answer: Yes
Is Flexible Treatment option (FTO) 1 feasible?
PREVIOUS QUESTION and ANSWER: Is BMP relocation feasible? - Answer: No
Is Flexible Treatment Option (FTO) 2 feasible?
PREVIOUS QUESTION and ANSWER: Is Flexible Treatment Option (FTO) 1 feasible? - Answer: No
Applicant attempts to comply with the following conditions:
Is karst present on the site?
If you are unsure, we recommend you review the guidance for karst in this manual. To retain your place in this flowchart, either open the karst guidance page in a new tab (right click on the link and select Open Link in New Tab), use the back arrow after visiting the karst guidance page, or use the Breadcrumbs at the top of the page.
PREVIOUS QUESTION and ANSWER:
or
Can a local unit of government (LGU) provide a higher level of engineering review to ensure a functioning system that prevents adverse impacts to groundwater?
PREVIOUS QUESTION and ANSWER: Is karst present on the site? - Answer: Yes
Is BMP relocation onsite to a location without karst feasible?
PREVIOUS QUESTION and ANSWER: Can a local unit of government (LGU) provide a higher level of engineering review to ensure a functioning system that prevents adverse impacts to groundwater? - Answer: No
Is Flexible Treatment Option (FTO) 2 feasible?
PREVIOUS QUESTION and ANSWER: Is BMP relocation onsite to a location without karst feasible? - Answer: No
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the following information
Applicant attempts to comply with the following conditions:
PREVIOUS STEP: It was determined that karst is present within 1000 feet of the site and the BMP cannot be reloacted so that it is more than 1000 feet from karst
Is shallow groundwater or shallow bedrock present on site?
If you are unsure, we recommend you review the guidance for shallow groundwater in this manual. To retain your place in this flowchart, either open the shallow groundwater guidance page in a new tab (right click on the link and select Open Link in New Tab), use the back arrow after visiting the shallow groundwater guidance page, or use the Breadcrumbs at the top of the page.
PREVIOUS QUESTION and ANSWER:
or
or
Conduct a detailed site investigation of shallow groundwater or shallow bedrock
PREVIOUS QUESTION and ANSWER: Is shallow groundwater or shallow bedrock present on site? - Answer: Yes
Is there more than 3 feet of soil depth from bottom of BMP to bedrock or groundwater (more than 10 feet is preferred)?
PREVIOUS STEP: You were asked to conduct a detailed site investigation of shallow groundwater or shallow bedrock
Is BMP relocation onsite to avoid shallow groundwater or shallow bedrock feasible?
PREVIOUS QUESTION and ANSWER: Is there more than 3 feet of soil depth from the bottom on the BMP to bedrock and groundwater (more than 10 feet is preferred)? - Answer: No
Can the BMP be raised?
PREVIOUS QUESTION and ANSWER: Is BMP relocation onsite to avoid shallow groundwater and shallow bedrock feasible? - Answer: No
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the following information
PREVIOUS STEP: It was determined that shallow groundwater or shallow bedrock is present within 3 feet of the bottom of the BMP and the BMP cannot be relocated or raised in elevation to achieve a 3 foot or greater separation from bedrock or groundwater.
Raise BMP enough to ensure 3 feet (preferably 10 feet) of soil between bottom of BMP and top of bedrock and groundwater
PREVIOUS QUESTION and ANSWER: Can the BMP be raised? Answer - Yes
Is there presence of contaminated soils and/or contaminated groundwater, or hotspot runoff?
PREVIOUS QUESTION and ANSWER:
or
or
or
Can hotspot or contamination be isolated or remediated to mitigate risk of increased contamination?
PREVIOUS QUESTION and ANSWER: Is there presence of contaminated soils and/or contaminated groundwater, or hotspot runoff? - Answer: Yes
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the following information
PREVIOUS STEP: It was determined that contaminated soil, contaminated groundwater, or hotspot runoff is present on the site and cannot be isolated or mitigated.
Are there very low infiltrating soils (less than 0.2 inches per hour) on site?
PREVIOUS QUESTION and ANSWER:
or
Is BMP relocation onsite to a higher-infiltrating location feasible?
PREVIOUS QUESTION and ANSWER: Are there very low infiltrating soils (less than 0.2 inches per hour) on site? - Answer: Yes
Can BMP be sized to drain dry within 48 hours (24 hours in locations that are tributary to trout streams)?
PREVIOUS QUESTION and ANSWER: Is BMP relocation onsite to a higher-infiltrating location feasible? - Answer: No
Provide soil boring or infiltration test results documenting low-infiltration soils.
PREVIOUS QUESTION and ANSWER: Can BMP be sized to drain within 48 hours (24 hours in locations that are tributary to trout streams)? Answer: No
Is Flexible Treatment Alternative No 1 feasible, allowing BMP to drain in 48 hours?
PREVIOUS STEP: You were asked to provide soil boring or infiltration test results documenting low-infiltration soils.
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the following information
PREVIOUS STEP: It was determined that soils on the site have an infiltration rate of less than 0.2 inches per hour, the BMP cannot be relocated to areas with a higher infiltration rate, and the BMP cannot be sized to drain within 48 hours (24 hours in locations that are tributary to trout streams)
Are there very high infiltrating soils (more than 8 inches per hour) on site?
PREVIOUS QUESTION and ANSWER:
or
or
Is BMP relocation onsite to a lower-infiltrating location feasible?
PREVIOUS QUESTION and ANSWER: Are there very high infiltrating soils (more than 8 inches per hour) on site? - Answer: Yes
Can subgrade be modified to slow the rate of infiltration to less than 8 inches per hour?
PREVIOUS QUESTION and ANSWER: Is BMP relocation onsite to a lower-infiltrating location feasible? - Answer: No
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the following information
PREVIOUS QUESTION and ANSWER: It was determined that soils on the site have an infiltration rate greater than 8 inches per hour, the BMP cannot be relocated to an area with an infiltration rate lower than 8 inches per hour, or the subgrade cannot be modified to slow the infiltration rate to less than 8 inches per hour
Are there adverse surface water hydrologic impacts from infiltration practices (e.g. impacting perched wetland)?
PREVIOUS QUESTION and ANSWER: Are there very high infiltrating soils (greater than 8 inches per hour) present on site)? - Answer: No or
or
Can the BMP be relocated to avoid adverse hydrologic impacts?
PREVIOUS QUESTION and ANSWER: Are there adverse surface water hydrologic impacts from infiltration practices (e.g. impacting perched wetland)? - Answer: Yes
Would BMPs accomodating Flexible treatment option 1 avoid adverse hydrologic impacts?
PREVIOUS QUESTION and ANSWER: Can the BMP be relocated to avoid adverse hydrologic impacts? - Answer: No
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the following information
Applicant attempts to comply with the following conditions:
Complete design using the following performance goals
Do the following conditions apply?
and
Do the following conditions apply?
and
PREVIOUS QUESTION and ANSWER: You determined that Flexible Treatment Option 2 is feasible and there are no limitations resulting from zoning and land use requirements.
Do any of the following conditions apply? (NOTE: If any condition applies, you do not need to answer the remaining questions.)
Do the following conditions apply?
and
PREVIOUS QUESTION and ANSWER: You determined that Flexible Treatment Option 2 is feasible and there are no limitations resulting from zoning and land use requirements.
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the foillowing information
PREVIOUS STEP: It was determined that the site is located within a DWSMA, wellhead protection area or within 200 feet of a drinking water well and infiltration is not allowed by the LGU.
Do any of the following conditions apply? (NOTE: If any condition applies, you do not need to answer the remaining questions.)
PREVIOUS STEP: You determined that flexible Treatment option 1 is feasible.
Is Flexible Treatment Option 2 feasible?
Applicant attempts to comply with the following conditions:
Do the following conditions apply?
PREVIOUS QUESTION and ANSWER: Is Flexible Treatment Alternative No 1 feasible, allowing BMP to drain in 48 hours? - Answer: Yes
Do the following conditions apply?
Are there existing or proposed structures or infrastructure that make Flexible Treatment Option 1 not feasible?
PREVIOUS STEP: You determined that flexible Treatment option 1 is feasible.
Do any of the following conditions apply? (NOTE: If any condition applies, you do not need to answer the remaining questions.)
PREVIOUS STEP: You determined that Flexible Treatment Option 1 is feasible.
Do the following conditions apply?
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the following information
PREVIOUS STEP: It was determined that
Select Flexible treatment Option 2
Applicant attempts to comply with the following conditions:
Provide the following information
PREVIOUS STEP: It was determined that
Is Flexible Treatment Option (FTO) 2 feasible?
PREVIOUS QUESTION and ANSWER: Can the BMP be raised? - Answer: No