Use this link to access .pdf diagrams of CADD drawings.
Before deciding to use a swale practice for stormwater management, it is helpful to consider several items that bear on the feasibility of using such a device at a given location. This section describes considerations in making an initial judgment as to whether or not a wet swale practice is the appropriate BMP for the site.
The RECOMMENDED maximum drainage area is typically 5 acres.
Unless slope stability calculations demonstrate otherwise (for guidance on calculating slope stability, see [1], [2], [3]), it is HIGHLY RECOMMENDED that swales be located a minimum horizontal distance of 200 feet from down-gradient slopes greater than 20 percent, and that slopes in contributing drainage areas be limited to 15 percent.
In general, there is no minimum separation distance required with wet swales and wetland channels. However, some source water protection requirements may dictate a separation distance if there is a sensitive underlying aquifer, which means that a liner might be required for portions of the swale or channel with standing water. A Level 2 liner is recommended. A field soil properties investigation is HIGHLY RECOMMENDED.
If wet swales are used in karst areas, it is RECOMMENDED that maximum pool depths be 3 to 5 feet. Impermeable liners maybe needed. Geotechnical investigations are necessary in karst areas.
See NRCS Web Soil Survey for hydrologic soil descriptions for the swale location. C and D soils are potentially suitable for wet swales. Infiltration abstractions are considered negligible in these conditions.
Several considerations are made in this section for the conceptual design of swales types. Further design guidance and specifications is made in the following sections.
It is HIGHLY RECOMMENDED that the designer provides non-erosive flow velocities within the swale and at the outlet point to reduce downstream erosion. During the 10-year or 25-year storm (depending on local drainage criteria), discharge velocity should be kept below 4 feet per second for established vegetated channels. Erosion control matting or rock should be specified if higher velocities are expected.
If there is space for pretreatment prior to the swale it should be evaluated. See the pretreatment section for more information.
Although local drainage criteria may require a certain frequency event be used in the design, it is HIGHLY RECOMMENDED that larger events be considered depending on the adjacent property and associated risks.
Stormwater treatment in swales varies by design, relying on several functions. Organic and mineral sediments suspended in stormwater flows are deposited onto the swale bottom, depending on their size and mass as well as water retention time in a process termed sedimentation. Though swales generally do not detain or retain water for extended periods, this function can be enhanced through the use of check dams or weirs that hold back flows for a design period.
A second function in pollutant removal is sorption of particulate matter via the swales soils and vegetation as it passes through the system. Wet swales also provide opportunity for plant uptake of pollutants.
Wet swales are not considered a volume reduction practice, though some volume reduction can occur through evapotranspiration.
Vegetation plays a crucial role in swale treatment capacity, flow attenuation and as well as in providing stabilization of the swale itself (i.e., erosion control). It is HIGHLY RECOMMENDED that preference is given to robust native, non-clump forming grasses as the predominant plant type within the swale flow area. Care must also be taken to consider species selection in light of sun exposure duration/timing as well as soil moisture, ponding depth and ponding duration. Special considerations for wet swales include plants tolerant of wet conditions and salt spray or runoff with elevated concentrations of sodium and chloride.
Swales can be effectively integrated into the site planning process, and aesthetically designed as attractive green spaces planted with native vegetation. Because vegetation is fundamental to the performance and function of the swale, aesthetically chosen vegetation may only be possible on the surface tops of the swales.
Considering management of snow, the following are recommended
For more information and example photos, see the section on snow and ice management.
Swales do not pose any major safety hazards. Potential hazards could occur from the steep side slope and rock checks of the swales if they are close to pedestrian traffic or roadways with no shoulders.
The use of temporary erosion control materials is REQUIRED in the design and construction of all swale types to allow for the establishment of firmly-rooted, dense vegetative cover. The swale bottom and side slopes up to the 10-yr event should use robust erosion control matting that can resists the expected shear stresses associated with channelized flows. The matting should have a minimum life expectancy of three years. Upper banks of the swale slope should be protected by either similar matting or a straw/coconut blend erosion control blanket. See MNDOT specifications for guidance on selection of erosion control products.
Rock (MNDOT – specs)
Weir (MNDOT – specs)
Plants (MNDOT specs)
Refer to the vegetation section of the manual for selection of Minnesota native plants to be used in swales. Care must be taken to specify plants for their position in the system (swale bottom, side slopes and buffer). Preference towards robust non-clump forming grasses or sedges should be given to the swale bottom that can withstand flow forces as well as provide adequate filtration functions. It is also important to understand draw-down time not only within the channel itself, but in either in-situ soils or the filter media as plants have variable tolerance to the depth and duration of inundation as well as soil moisture period. Lastly, care should be taken to understand sun exposure requirements of various plants to ensure a robust, dense establishment of vegetative cover.
Open vegetated swale materials specifications.
Link to this table
Parameter | Specification | Size | Note | Design application |
---|---|---|---|---|
Dry swale soil | USCS; ML, SM, SC | n/a | soil with a higher percent organic content is preferred | dry swale, step pool |
Dry swale sand | ASTM C-33 fine aggregate concrete sand | 0.02” to 0.04” | dry swale, step pool | |
Check dam (pressure treated) | AWPA Standard C6 | 6” by 6” or 8” by 8” | do not coat with creosote; embed at least 3’ into side slopes | dry swale, wet swale, step pool |
Check Dam (natural wood) | Black Locust, Red Mulberry, Cedars, Catalpa, White Oak, Chestnut Oak, Black Walnut | 6” to 12” diameter; notch as necessary | do not use the following, as these species have a predisposition towards rot: Ash, Beech, Birch, Elm, Hackberry, Hemlock, Hickories, Maples, Red and Black Oak, Pines, Poplar, Spruce, Sweetgum, Willow | dry swale, wet swale, step pool |
Filter Strip sand/gravel pervious berm | sand: per dry swale sand gravel; AASHTO M-43 | sand: 0.02” to 0.04” gravel: 1/2” to 1” | Mix with approximately 25% loam soil to support grass cover crop; see Bioretention planting soil notes for more detail | dry swale, step pool |
Pea gravel diaphragm and curtain drain | ASTM D 448 | varies (No. 6) or (1/8” to 3/8”) | use clean bank-run gravel | dry swale, step pool |
Underdrain gravel | per pre-cast manufacturer | 1.5” to 3.5” | dry swale, step pool | |
Underdrain | ASTM D-1785 or AASHTO M-278 | 6” rigid Schedule 40 PVC | 3/8” perf. @ 6” o.c.; 4 holes per row | dry swale, step pool |
Rip rap | per local criteria | size per requirements based on 10- year design flow | dry swale, wet swale, step pool | |
It is important to acknowledge that each site has unique and defining features that require site-specific design and analysis. The guidance provided below is intended to provide the fundamentals for designing swale systems to meet regulatory requirements but is not intended to substitute engineering judgment regarding the validity and feasibility associated with site-specific implementation. Designers need to be familiar with the hydrologic and hydraulic engineering principles that are the foundation of the design and they should also enlist the expertise of qualified individuals in stormwater management and conveyance system plantings with respect to developing appropriate planting plans and habitat improvement features.
Considering basic issues for initial suitability screening, make a preliminary judgment as to whether site conditions are appropriate for the use of a swale, and identify its function in the overall treatment system.
A. Consider basic issues for initial suitability screening, including:
B. Determine how the swale will fit into the overall stormwater treatment system, including:
A. Determine whether a media filter must comply with the MPCA Construction Stormwater General Permit (CGP). To determine if permit compliance is required, see Permit Coverage and Limitations.
B. Check with local officials, watershed organizations, and other agencies to determine if there are any additional restrictions and/or surface water or watershed requirements that may apply.
See Major design elements
Once the physical suitability evaluation is complete, it is HIGHLY RECOMMENDED that the better site design principles be applied in sizing and locating the wet swale practice(s) on the development site. Given the drainage area, select the appropriate swale practice for the first iteration of the design process.
Note: Information collected during the physical suitability evaluation (see Step 1) should be used to explore the potential for multiple swale practices versus relying on a single facility. Compute watershed runoff values.
If the swale is being designed to meet the requirements of the MPCA Permit, the REQUIRED treatment volume is the water quality volume of 1 inch of runoff from the new impervious surfaces created from the project. If part of the overall Vwq is to be treated by other BMPs, subtract that portion from the Vwq to determine the part of the Vwq to be treated by the dry swale.
For swales, compute the following design parameters:
A. Calculate the maximum discharge loading per foot of swale width
\(q = (0.00236/n) · Y · 1.67 · S · 0.5 \)
Where:
B. Use a recommended hydrologic model to compute Qwq
C. Minimum swale length (in feet) = Qwq / q
Where:
Check for erosive velocities and modify design as appropriate based on local conveyance regulations. Provide 6 inches of freeboard.
Design control to pass Vwq in 48 hours.
Inlets to swales must be provided with energy dissipaters such as riprap or geotextile reinforcement. Pre-treatment of runoff is typically provided by a sediment forebay located at the inlet.
Follow the design procedures identified in the Unified Sizing Criteria section of the Manual to determine the volume control and peak discharge requirements for water quality, recharge (not required), channel protection, overbank flood and extreme storm.
Model the proposed development scenario using a surface water model appropriate for the hydrologic and hydraulic design considerations specific to the site. This includes defining the parameters of the swale practice defined above: ponding elevation and area (defines the ponding volume), filtration rate and method of application (effective filtration area), and outlet structure and/or flow diversion information. The results of this analysis can be used to determine whether or not the proposed design meets the applicable requirements. If not, the design will have to be re-evaluated.
{{:Swale systems shall be sufficient to filter a water quality volume of 1 inch of runoff from the new impervious surfaces created by the project. If this criterion is not met, increase the storage volume of the filtration practice or treat excess water quality volume (Vwq) in an upstream or downstream BMP (see Step 5).}}
A landscaping plan for a wet swale should be prepared to indicate how the enhanced swale system will be stabilized and established with vegetation. Landscape design should specify proper species and based on specific site, soils, sun exposure and hydric conditions present along the channel. Further information on plant selection and use can be found in the Minnesota plant lists section.
See Operation and Maintenance section for guidance on preparing an O&M plan.
See Cost Considerations section for guidance on preparing a cost estimate that includes both construction and maintenance costs.