Excerpt from Table 2575-4, Required Corrective Action
Link to this table
Item |
Corrective Action Required if: |
Corrective Action |
Turf Reinforcement Mat |
- Wrong TRM installed
- Missing certificate of compliance
- Missing anchoring devices
- Insufficient anchoring devices
- Missing head anchor embedment
- Missing edge anchor embedment
- Improper or insufficient overlap of adjoining mat units
- Improper soil infill depth (about 1 inch)
- Improper soil type
- Improper hydraulic mulch RFM infill
- Wrong rolled erosion control cover
|
- Remove incorrect and replace with proper TRM
- Cease operations and secure certificate. Else remove and replace
- Install additional anchoring devices as per plan or Manufacturer
- Install additional anchoring devices as per plan or Manufacturer
- Entrench leading edge and anchor correctly
- Entrench side edge and anchor correctly
- Provide proper joints and overlaps
- Apply additional screen topsoil or screed excess
- Cease operations and contact OES
- Apply additional hydraulic mulch Type RFM to manufacturer specification
- Remove improper RECP and apply correct product
|