(Created page with " ===Construction and Maintenance Costs=== <p>Chapter 6 outlines a cost estimation method which site planners could use to compare the relative construction and maintenance cos...")
 
 
(5 intermediate revisions by 2 users not shown)
Line 1: Line 1:
  
 
===Construction and Maintenance Costs===
 
===Construction and Maintenance Costs===
<p>Chapter 6 outlines a cost estimation method which site planners could use to compare the relative construction and maintenance costs for structural best management practices. These curves are excellent for purposes of comparison; however, it is recommended that construction and maintenance budgets should be based on site specific information. Utilizing the table below and the cost [[BIORETENTION - Construction inspection checklist|estimation worksheet]], will allow designers to more accurately estimate the cost of a filtration BMP.</p>
+
These curves are excellent for purposes of comparison; however, it is recommended that construction and maintenance budgets should be based on site specific information. Utilizing the table below and the cost [[Bioretention - construction inspection checklist|estimation worksheet]], will allow designers to more accurately estimate the cost of a filtration BMP.</p>
  
 
{{:Cost components for filtration practices}}
 
{{:Cost components for filtration practices}}
 +
 +
[[Category:Level 2 - Best management practices/Cost benefit]]
 +
[[Category:Level 3 - Best management practices/Structural practices/Dry swale]]
 +
[[Category:Level 3 - Best management practices/Structural practices/Step pool]]
 +
[[Category:Level 3 - Best management practices/Structural practices/Wet swale]]

Latest revision as of 13:08, 14 February 2023

Construction and Maintenance Costs

These curves are excellent for purposes of comparison; however, it is recommended that construction and maintenance budgets should be based on site specific information. Utilizing the table below and the cost estimation worksheet, will allow designers to more accurately estimate the cost of a filtration BMP.

Cost components for filtration practices.
Link to this table

Implementation Stage Primary Cost Components Basic Cost Estimate Other Considerations
Site Preparation Tree & plant protection Protection Cost ($/acre) x Affected Area (acre) Removal of existing structures, topsoil removal and stockpiling
Topsoil salvage Salvage cost ($/acre) x Affected Area (acre)
Clearing & grubbing Clearing Cost ($/acre) x Affected Area (acre)
Site Formation Excavation / grading X-ft Depth Excavation Cost ($/acre) x Area (acre) Soil & rock fill Hauling material material, tunneling
Hauling material offsite Excavation Cost x (% of Material to be hauled away)
Structural Components Under-drains Under-drain cost ($/lineal foot) x length of device Pipes, catchbasins, manholes, valves, vaults
Vault structure (for media filters) ($/structure)
Media (for media filters) Media cost ($/cubic yard) X filter volume (cubic yard)
Inlet structure (for vegetative filters ($/structure)
Outlet structure (for vegetative filters) ($/structure)
Site Restoration Filter strip Sod cost ($/square foot) x filter strip area Tree protection, soil amendments, seed bed preparation, trails
Soil preparation Topsoil or amendment cost ($/acre) x Area (acre)
Seeding Seeding Cost ($/acre) x Seeded Area (acre)
Planting / transplanting Planting Cost ($/acre) x Planted Area (acre)
Annual Operation, Maintenance, and Inspection Debris removal Removal Cost ($/acre) x Area (acre) x Frequency (2x / 1yr) Vegetation maintenance, cleaning of structures
Sediment removal Removal Cost ($/acre) x Area (acre) x Frequency (1x / 5yr)
Gate / valve operation Operation Cost ($) x Operation Frequency (2x / 1 yr)
Inspection Inspection Cost ($) x Inspection Frequency (6x / 1 yr)
Mowing (for some vegetative filters) Mowing Cost ($) x Mowing Frequency (4x / 1 yr)

This page was last edited on 14 February 2023, at 13:08.