m |
|||
Line 4: | Line 4: | ||
*clogged, inlet, outlet or under-drains | *clogged, inlet, outlet or under-drains | ||
− | ==Design | + | ==Design phase maintenance considerations== |
Implicit in the design guidance in the previous sections is the fact that many design elements of filtering systems can minimize the maintenance burden and maintain pollutant removal efficiency. Key examples include limiting drainage area, providing easy site access (''REQUIRED''), and providing adequate pre-treatment (''REQUIRED''). | Implicit in the design guidance in the previous sections is the fact that many design elements of filtering systems can minimize the maintenance burden and maintain pollutant removal efficiency. Key examples include limiting drainage area, providing easy site access (''REQUIRED''), and providing adequate pre-treatment (''REQUIRED''). | ||
− | ==Construction | + | ==Construction phase maintenance== |
Proper construction methods and sequencing play a significant role in reducing problems with operation and maintenance (O&M). In particular, with filter construction the most important action for preventing operation and maintenance difficulties is to ensure that the contributing drainage area has been fully stabilized prior to bringing the practice on line (this is a ''REQUIRED'' practice). | Proper construction methods and sequencing play a significant role in reducing problems with operation and maintenance (O&M). In particular, with filter construction the most important action for preventing operation and maintenance difficulties is to ensure that the contributing drainage area has been fully stabilized prior to bringing the practice on line (this is a ''REQUIRED'' practice). | ||
<p>Inspections during construction are needed to ensure the filter practice is built in accordance with the approved design and standards and specifications. Detailed inspection checklists should be used that include sign-offs by qualified individuals at critical stages of construction, to verify the contractor’s interpretation of the plan is acceptable with the designer. Example construction phase inspection checklists exist for [[Bioretention - construction inspection checklist|bioretention]], [[Media filter system - construction inspection checklist|media filter systems]], and [[Vegetative filter system - construction inspection checklist|vegetative filter systems]].</p> | <p>Inspections during construction are needed to ensure the filter practice is built in accordance with the approved design and standards and specifications. Detailed inspection checklists should be used that include sign-offs by qualified individuals at critical stages of construction, to verify the contractor’s interpretation of the plan is acceptable with the designer. Example construction phase inspection checklists exist for [[Bioretention - construction inspection checklist|bioretention]], [[Media filter system - construction inspection checklist|media filter systems]], and [[Vegetative filter system - construction inspection checklist|vegetative filter systems]].</p> |
The most frequently cited maintenance concern for filters is surface and underdrain clogging caused by organic matter, fine silts, hydrocarbons, and algal matter. Common operational problems include:
Implicit in the design guidance in the previous sections is the fact that many design elements of filtering systems can minimize the maintenance burden and maintain pollutant removal efficiency. Key examples include limiting drainage area, providing easy site access (REQUIRED), and providing adequate pre-treatment (REQUIRED).
Proper construction methods and sequencing play a significant role in reducing problems with operation and maintenance (O&M). In particular, with filter construction the most important action for preventing operation and maintenance difficulties is to ensure that the contributing drainage area has been fully stabilized prior to bringing the practice on line (this is a REQUIRED practice).
Inspections during construction are needed to ensure the filter practice is built in accordance with the approved design and standards and specifications. Detailed inspection checklists should be used that include sign-offs by qualified individuals at critical stages of construction, to verify the contractor’s interpretation of the plan is acceptable with the designer. Example construction phase inspection checklists exist for bioretention, media filter systems, and vegetative filter systems.
Proper maintenance is critical to the successful operation of a filtration practice. Without regular maintenance, filtration system media can become clogged, losing its ability to conduct water at the designed rate. This can lead to stagnant water, mosquito breeding habitat, and reduction or elimination of pollutant removal capacity.
Effective long-term operation of filtration practices necessitates a dedicated and routine maintenance schedule with clear guidelines and schedules. Some important post-construction considerations are provided below.
Example operation and maintenance checklists exist for bioretention, media filter systems, and vegetative filter systems. The following table provides a more detailed checklist of maintenance activities and associated schedule along with RECOMMENDED maintenance standards.
Recommended maintenance activities for media filters (Sources: WMI, 1997; Pitt, 1997).
Link to this table
Activity | Schedule |
---|---|
|
As needed |
|
Monthly |
|
Annually |
|
3 to 5 years |