This site is currently undergoing final review. For more information, open this link.
This page is under final review through February, 2016
This page provides guidance and recommendations for determining the appropriateness of infiltrating stormwater in a Drinking Water Supply Management Area (DWSMA). For more information on source water protection see Minnesota Department of Health.
You can access a flowchart to be used for determining the appropriateness of infiltration in DWSMAs at File:Flow Chart - MDH Stormwater Guidance for Sites in Drinking Water Supply Management Areas.pdf
Definitions
Example map illustrating different protection designations for public supply wells with wellhead protection plans.
The figure at the right illustrates protection designations used to manage public water supply wells that have wellhead protection plans.
- Drinking Water Supply Management Area (DWSMA) - the surface and subsurface area surrounding a public water supply well, including the wellhead protection area, that must be managed by the entity identified in a wellhead protection plan. This area is delineated using identifiable landmarks that reflect the scientifically calculated wellhead protection area boundaries as closely as possible.
- Drinking Water Supply Management Area Vulnerability. An assessment of the likelihood that the aquifer within the DWSMA is subject to impact from overlying land and water uses. It is based upon criteria that are specified under Minnesota Rules, part 4720.5210, subpart 3.
- Emergency Response Area (ERA). The part of the wellhead protection area that is defined by a one-year time of travel within the aquifer that is used by the public water supply well (Minnesota Rules, part 4720.5250, subpart 3). It is used to set priorities for managing potential contamination sources within the DWSMA. This area is particularly relevant for assessing impacts from potential sources of pathogen contamination because this time of travel is believed to closely correspond with the survival period of many pathogens.
- Public water supply well – a drinking water well as defined in Minnesota Statutes, section 103I.005, subdivision 21, that serves a public water supply.
- Time of travel - means the amount of time over which groundwater will move through a portion of an aquifer to recharge a well in use. Note this definition does not consider travel time within the unsaturated (vadose) zone.
- Vulnerable public supply well – a public water supply well is vulnerable if:
- the well water contains ten (10) milligrams per liter or more nitrate plus nitrite nitrogen;
- the well water contains quantifiable levels of pathogens as defined in part 7040.0100, subpart 26, or chemical compounds that indicate groundwater degradation as defined in Minnesota Statutes, section 103H.005, subdivision 6;
- the well water contains one tritium unit or more when measured with an enriched tritium detection method; or
- an enriched tritium analysis of the well water has not been performed within the past ten years; and
- information on the well construction is not available; or
- the geological material from the land surface to where the groundwater enters the public water supply well is:
- fractured bedrock;
- solution weathered bedrock;
- sandstone bedrock;
- unconsolidated material 0.062 millimeters (fine sand) or larger; or
- a combination of the materials specified in units (a) to (d).
- Wellhead Protection Area (WHPA) – the surface and subsurface area surrounding a well or well field that supplies a public water system, through which contaminants are likely to move toward and reach the well or well field (Minnesota Statutes, section 103I.005, subdivision 24).
- Wellhead Protection Plan - a document that provides for the protection of a public water supply, is submitted to the department, is implemented by the public water supplier, and complies with:
- the wellhead protection elements specified in the 1986 amendments to the federal Safe Drinking Water Act, United States Code, title 42, chapter 6A, subchapter XII, part C, section 300h-7 (1986 and as subsequently amended); and
- parts 4720.5200 to 4720.5290.
Step-by-step process for determining applicability of infiltration
The Minnesota Department of Health and Minnesota Pollution Control Agency developed joint guidance for determining the applicability of infiltration in a Drinking Water Supply Management Area (DWSMA). A step-by-step process for determining if infiltration is allowed and appropriate in a DWSMA is shown on the right. You can also access this flowchart at File:Flow Chart - MDH Stormwater Guidance for Sites in Drinking Water Supply Management Areas.pdf. Guidance and additional information to support the flowchart is found at File:Evaluating Proposed Stormwater Infiltration Projects in Vulnerable Wellhead Protection Areas.docx.
Step 1a: Is the site located in a DWSMA?
- If Yes, proceed to Step 2
- If No, proceed to Step 3
Step 2: Is there a Local Government Unit with a current Municipal Separate Storm Sewer System permit that allows infiltration?
Step 3: Is the site in a portion of the DWSMA that exhibits very high, high, or moderate vulnerability?
Step 4: Is the site in the Wellhead Protection Area (WHPA) of an aquifer exhibiting fracture flow or karst and less than 50 feet of unfractured geologic cover?
- If Yes, infiltration is generally not appropriate due to the potential for adverse effects to the aquifer used for drinking water supply. Consider other stormwater handling procedures such as stormwater retention and conveyance outside of the WHPA or moving the infiltration area to a non-vulnerable part of the DWSMA. For more information, discuss with MDH subject matter experts or the hydrologist or planner for the DWSMA or with stormwater staff at the MPCA.
- If No, proceed to Step 5
Step 5: Is the site within the Emergency Response Area (ERA) and is vulnerability very high or high?
- If Yes, infiltration is generally not appropriate due to the potential for adverse effects to the aquifer used for drinking water supply. Consider other stormwater handling procedures such as stormwater retention and conveyance outside of the WHPA or moving the infiltration area to a non-vulnerable part of the DWSMA. For more information, discuss with MDH subject matter experts or the hydrologist or planner for the DWSMA or with stormwater staff at the MPCA.
- If No, proceed to Step 6
Step 6: Is the site within a WHPA and either outside the ERA or vulnerability is moderate?
Step 7: Will runoff from potential stormwater hotspots or highways enter the infiltration practice?
- If Yes, proceed observing state and local stormwater requirements. See additional requirements and guidance below.
- If No, infiltration is generally not appropriate due to the potential for adverse effects to the aquifer used for drinking water supply. Consider other stormwater handling procedures such as stormwater retention and conveyance outside of the WHPA or moving the infiltration area to a non-vulnerable part of the DWSMA. For more information, discuss with MDH subject matter experts or the hydrologist or planner for the DWSMA or with stormwater staff at the MPCA.
Additional requirements and guidance
The following requirements and guidance apply to infiltration practices regardless of whether the site is located in a DWSMA.
Prohibitions to infiltration under the Construction Stormwater permit
If the site requires a Construction Stormwater General Permit, stormwater infiltration is prohibited in the following areas regardless of whether the site is located in a DWSMA.
- Areas that receive discharges from vehicle fueling and maintenance.
- Areas with less than three (3) feet of separation distance from the bottom of the infiltration system to the elevation of the seasonally saturated soils or the top of bedrock.
- Areas that receive discharges from industrial facilities that are not authorized to infiltrate industrial stormwater under an NPDES/SDS Industrial Stormwater Permit issued by the MPCA.
- Areas where high levels of contaminants in soil or groundwater will be mobilized by the infiltrating stormwater.
- Areas of predominately Hydrologic Soil Group D (clay) soils unless allowed by a local unit of government with a current MS4 permit.
- Areas within 1,000 feet up‐gradient, or 100 feet down‐gradient of active karst features unless allowed by a local unit of government with a current MS4 permit.
- Areas where soil infiltration rates are more than 8.3 inches per hour unless soils are amended to slow the infiltration rate below 8.3 inches per hour or as allowed by a local unit of government with a current MS4 permit.
For those conditions above in which a local unit of government with a Municipal Separate Storm Sewer System (MS4) permit allows infiltration, follow the recommendations for infiltration practices in a DWSMA.
Recommendations for infiltrating stormwater in DWSMAs
The following are recommendations for infiltration practices in a DWSMA regardless of whether the above step-by-step process indicates infiltration is appropriate or a Construction Stormwater permit is required.
- Ensure that separation distances are met and that existing or proposed structures or infrastructure (e.g. rate control BMPs, utilities, buildings, roadway, easements) do not prevent infiltration.
- If there is a potential for the high water table or bedrock to be within 6 feet of the bottom of proposed infiltration practices, follow guidelines in the Minnesota Stormwater Manual for conducting site investigations and managing infiltration in these areas.
- If there is the potential for presence of contaminated soils, contaminated groundwater, and/or hotspot runoff, follow guidelines in the Minnesota Stormwater Manual for conducting site investigations and managing infiltration in these areas.
- If there is a potential for presence of soils with steady-state infiltration rates less than 0.2 inches per hour, follow guidelines in the Minnesota Stormwater Manual for conducting site investigations and managing infiltration in these areas.
- If infiltration could result in adverse surface water hydrologic impacts, such as impacting a perched wetland, minimize infiltration to a point where adverse surface water hydrologic impacts are avoided.
- If the infiltration practice is constructed in industrial, commercial, or transportation land uses, ensure that emergency procedures for containment of spills are established and acceptable.
- Infiltration is not recommended in areas that receive discharges from vehicle fueling and maintenance.
- Infiltration is not recommended in areas that receive discharges from industrial facilities that are not authorized to infiltrate industrial stormwater under an NPDES/SDS Industrial Stormwater Permit issued by the MPCA.
- Infiltration is not recommended in areas within 1,000 feet up‐gradient, or 100 feet down‐gradient of active karst features. If infiltration is being considered, follow stormwater management guidelines for karst areas.
- Infiltration is not recommended in areas where soil infiltration rates are more than 8.3 inches per hour unless soils are amended to slow the infiltration rate below 8.3 inches per hour or as allowed by a local unit of government with a current MS4 permit.
Maps
File:Using the MS4 map tool.png Screen shot illustrating DWSMAs in the MS4 mapping tool. To view the DWSMA layer, ensure the layer is visible and expand the layer to see the vulnerability classifications. Turn off other layers as needed. the DWSMA layer may not appear until the map has been zoomed in to a certain level. Use the zoom and pan features in the upper left part of the tool.
- The MS4 mapping tool includes a coverage illustrating DWSMAs and their vulnerability.
- Shapefiles and maps showing DWSMAs, DWSMA vulnerability, Emergency Response Areas, and Wellhead protection Areas can be found on an MDH website.
Related pages