Typical maintenance problems and activities for infiltration practices
Link to this table
Inspection Focus | Common Maintenance Problems | Maintenance Activity | Recommended Maintenance Schedule | Applicable Infiltration Practices1 |
---|---|---|---|---|
Drainage Area and Drawdown Time | Clogging, sediment deposition | Ensure that contributing catchment areas to practice, and inlets are clear of debris | Monthly | 1,2,3,4,5,6,7 |
Erosion of catchment area contributing significant amount of sediment | In case of severely reduced drawdown time, scrape bottom of basin and remove sediment. Disc or otherwise aerate/scarify basin bottom. De-thatch if basin bottom is turf grass. Restore original design cross section or revise section to increase infiltration rate and restore with vegetation as necessary. | Upon identification of drawdown times longer than 48 hours or upon complete failure | 1,2,3,4,5,6 | |
Pretreatment | Pretreatment screens or sumps reach capacity | Remove sediment and oil/grease from pretreatment devices/structures. | Minimum yearly or as per manufacturer's recommendations | 1,2,3,4,5 |
Vegetative filter strip failure | Reduce height of vegetative filter strip that may be limiting in‐flow. Re‐establish vegetation to prevent erosion. Leave practice off‐line until full reestablishment. | Mow grass filter strips monthly. Restore as necessary | 1,2,4,6 | |
Site Erosion | Scouring at inlets | Correct earthwork to promote non‐erosive flows that are evenly distributed | As necessary | 1,2,3,6 |
Unexpected flow paths into practice | Correct earthwork to eliminate unexpected drainage or created additional stable inlets as necessary | As necessary | 1,2,3,6 | |
Vegetation | Reduced drawdown time damaging plants | Correct drainage issues as described above | Replace with appropriate plants after correction of drainage issues | 2,6,8 |
Severe weed establishment | Limit the ability for noxious weed establishment by properly mowing, mulching or timely herbicide or hand weeding. Refer to the MDA Noxious Weed List | Bi‐monthly April through October | 2,6,8 |
11=Infiltration Basin; 2=Bioinfiltration Basin; 3=Infiltration Trench; 4=Dry Well; 5=Underground Infiltration; 6=Dry Swale with Check Dams; 7=Permeable Pavement; 8=Tree Trench/Tree Box