This page provides guidance to help determine if and to what extent infiltration is feasible at a site. The discussion focuses on the physical ability to infiltrate stormwater runoff rather than determining the ability to meet a specific volume requirement of performance goal.
+
This page provides guidance to help determine if infiltration [[Glossary#B|Best Management Practices]] (BMPs) can be utilized at a site. [http://stormwater.pca.state.mn.us/index.php/BMPs_for_stormwater_infiltration Infiltration BMPs] include [[Bioretention|bioinfiltration]], [[Infiltration basin|infiltration basin]], [[Infiltration trench|infiltration trench]], underground infiltration, [[Permeable pavement|permeable pavement]], [https://stormwater.pca.state.mn.us/index.php?title=Dry_swale_(Grass_swale) dry swales], [https://stormwater.pca.state.mn.us/index.php?title=High-gradient_stormwater_step-pool_swale step pool swales], and [[Trees|tree trench or tree box with no underdrain]]. Note that some infiltration occurs in BMPs with [[Glossary#U|underdrains]], particularly if the underdrain is raised above the bottom of the BMP. If no infiltration is desired at a site, a [https://stormwater.pca.state.mn.us/index.php?title=Liners_for_stormwater_management liner] should be used.
  
{{alert|The [http://stormwater.pca.state.mn.us/index.php/III._STORMWATER_DISCHARGE_DESIGN_REQUIREMENTS#III.D._PERMANENT_STORMWATER_MANAGEMENT_SYSTEM Construction Stormwater General Permit] states “Where a project’s ultimate development replaces vegetation and/or other pervious surfaces with one (1) or more acres of cumulative impervious surface, the Permittee(s) must design the project so that the water quality volume of one (1) inch of runoff from the new impervious surfaces created by the project is retained on site”|alert-danger}}
+
Infiltration is often utilized at a site to meet a regulatory requirement or a performance goal for stormwater volume. The following discussion does not specifically focus on utilizing infiltration to meet a requirement or performance goal, although there is a section that provides information for [https://stormwater.pca.state.mn.us/index.php/Decision_tools_for_stormwater_infiltration#Determining_the_amount_of_infiltration_possible_at_a_site determining the amount of infiltration feasible at a site].
 +
 
 +
{{alert|The [[MN CSW Permit Section 15 Permanent Stormwater Treatment System|Construction Stormwater General Permit]] states “Permittees must design and construct a permanent stormwater treatment system to treat the [[MN CSW Permit Section 25 Definitions|water quality volume]] if the project's ultimate development replaces vegetation and/or other pervious surfaces creating a net increase of one (1) or more acres of cumulative [[MN CSW Permit Section 25 Definitions|impervious surface]]. Permittees must calculate the water quality volume as one (1) inch times the net increase of impervious surfaces created by the project."|alert-danger}}
 +
 
 +
The following table can be used to determine if infiltration is prohibited or not recommended. Discussion of conditions where infiltration may be acceptable when site constraints exist [https://stormwater.pca.state.mn.us/index.php?title=Decision_tools_for_stormwater_infiltration#Determine_if_infiltration_is_not_prohibited_but_is_not_recommended is provided below].
 +
 
 +
{{:Situations where infiltration is prohibited or not recommended}}
  
 
==Determine if infiltration is prohibited==
 
==Determine if infiltration is prohibited==
Line 9: Line 15:
 
*Determine if there are other prohibitions on infiltration. Infiltration is prohibited if any of the following conditions apply.
 
*Determine if there are other prohibitions on infiltration. Infiltration is prohibited if any of the following conditions apply.
 
**The infiltration practice (BMP) is less than 100 feet from a drinking water supply well in a sensitive aquifer or less than 50 feet from a drinking water well in a non-sensitive aquifer. ([http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_setback_%28separation%29_distances#Water_supply_wells link]).
 
**The infiltration practice (BMP) is less than 100 feet from a drinking water supply well in a sensitive aquifer or less than 50 feet from a drinking water well in a non-sensitive aquifer. ([http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_setback_%28separation%29_distances#Water_supply_wells link]).
 +
**The infiltration practice receives discharges from vehicle fueling and maintenance.
 
**A Construction Stormwater General (CGP) permit is required and any of the following conditions applies.
 
**A Construction Stormwater General (CGP) permit is required and any of the following conditions applies.
***The infiltration practice receives discharges from vehicle fueling and maintenance.
 
 
***There is less than three (3) feet of separation distance from the bottom of the infiltration system to the elevation of the seasonally saturated soils or the top of bedrock. ([http://stormwater.pca.state.mn.us/index.php/Shallow_soils_and_shallow_depth_to_bedrock link])
 
***There is less than three (3) feet of separation distance from the bottom of the infiltration system to the elevation of the seasonally saturated soils or the top of bedrock. ([http://stormwater.pca.state.mn.us/index.php/Shallow_soils_and_shallow_depth_to_bedrock link])
***The infiltration practice receives discharges from industrial facilities which are not authorized to infiltrate industrial stormwater under an NPDES/SDS Industrial Stormwater Permit issued by the MPCA. To determine if infiltration is allowed for a specific industrial sector or subsector, go to the [http://stormwater.pca.state.mn.us/index.php/PART_VII._SECTOR-SPECIFIC_REQUIREMENTS list of sectors], select the sector of interest, and review section 8 for that sector (''Use of Infiltration Devices and/or Industrial Stormwater Ponds for Stormwater Treatment and Disposal'')
+
***The infiltration practice receives discharges from industrial facilities which are not authorized to infiltrate industrial stormwater under an NPDES/SDS Industrial Stormwater Permit issued by the MPCA. To determine if infiltration is allowed for a specific industrial sector or subsector, go to the [https://stormwater.pca.state.mn.us/index.php?title=Industrial_stormwater_program list of sectors], select the sector of interest, and review section 8 for that sector (''Use of Infiltration Devices and/or Industrial Stormwater Ponds for Stormwater Treatment and Disposal'')
 
***The infiltration practice receives discharges from areas with high levels of contaminants in soil or groundwater and contaminants will be mobilized by the infiltrating stormwater. ([http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltrations_and_contaminated_soils_and_groundwater link])
 
***The infiltration practice receives discharges from areas with high levels of contaminants in soil or groundwater and contaminants will be mobilized by the infiltrating stormwater. ([http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltrations_and_contaminated_soils_and_groundwater link])
***The infiltration practice is located in areas of predominately Hydrologic Soil Group D (clay) soils unless allowed by a local unit of government with a current MS4 permit. ([http://stormwater.pca.state.mn.us/index.php/Soils_with_low_infiltration_capacity link])
+
***The infiltration practice is located in areas of predominately Hydrologic Soil Group D (clay) soils. ([http://stormwater.pca.state.mn.us/index.php/Soils_with_low_infiltration_capacity link])
***The infiltration practice is within 1,000 feet up‐gradient, or 100 feet down‐gradient of active karst features, unless allowed by a local unit of government with a current MS4 permit. ([http://stormwater.pca.state.mn.us/index.php/Karst link])
+
***The infiltration practice is within 1,000 feet up‐gradient, or 100 feet down‐gradient of active karst features. ([http://stormwater.pca.state.mn.us/index.php/Karst link])
***The infiltration practice is within a Drinking Water Supply Management Area (DWSMA) as defined in Minn. R. 4720.5100, subp. 13., unless allowed by a local unit of government with a current MS4 permit. ([http://stormwater.pca.state.mn.us/index.php/Stormwater_and_wellhead_protection link])
+
***The infiltration practice is in a Drinking Water Supply Management Area (DWSMA) as defined in [https://www.revisor.mn.gov/rules/?id=4720.5100 Minn. R. 4720.5100], subp. 13., if the system will be located:
***The infiltration practice is located in areas where soil infiltration rates are more than 8.3 inches per hour unless soils are amended to slow the infiltration rate below 8.3 inches per hour or as allowed by a local unit of government with a current MS4 permit.
+
****in an Emergency Response Area (ERA) within a DWSMA classified as having high or very high vulnerability as defined by the Minnesota Department of Health; or
 +
****in an ERA within a DWSMA classified as moderate vulnerability unless a regulated MS4 Permittee performed or approved a [https://stormwater.pca.state.mn.us/index.php?title=Guidance_and_recommendations_for_conducting_a_higher_level_of_engineering_review_for_stormwater_infiltration_in_DWSMAs_and_Wellhead_Protection_Areas higher level of engineering review] sufficient to provide a functioning treatment system and to prevent adverse impacts to groundwater; or
 +
****outside of an ERA within a DWSMA classified as having high or very high vulnerability, unless a regulated MS4 Permittee performed or approved a higher level of engineering review sufficient to provide a functioning treatment system and to prevent adverse impacts to groundwater. ([http://stormwater.pca.state.mn.us/index.php/Stormwater_and_wellhead_protection link])
 +
***The infiltration practice is located in areas where soil infiltration rates are more than 8.3 inches per hour unless soils are amended to slow the infiltration rate below 8.3 inches per hour.
  
 
==Determine if infiltration is not prohibited but is not recommended==
 
==Determine if infiltration is not prohibited but is not recommended==
If infiltration is not prohibited but any of the following conditions apply, infiltration is not recommended.
+
If infiltration is not prohibited but any of the following conditions apply, infiltration is not recommended. In some cases, infiltration may be acceptable if the practice is modified, as described below.
*There is less than three (3) feet of separation distance from the bottom of the infiltration practice to the elevation of the seasonally saturated soils or the top of bedrock and
+
*A Construction Stormwater General (CGP) permit is not required but one or more of the following conditions applies.
**the practice cannot be raised to achieve three (3) feet of separation, or
+
**There is less than three (3) feet of separation distance from the bottom of the infiltration practice to the elevation of the seasonally saturated soils or the top of bedrock.
**the practice cannot be relocated to achieve three (3) feet of separation.
+
**The infiltration practice is located in areas of predominately Hydrologic Soil Group D (clay) soils. Modifications to allow some infiltration include replacing the soil with permeable media or using a raised underdrain or internal water storage ([https://stormwater.pca.state.mn.us/index.php?title=Bioretention_terminology see here]).
*The infiltration practice is located in areas of predominately Hydrologic Soil Group D (clay) soils and
+
**The infiltration practice is located in areas where soil infiltration rates are more than 8.3 inches per hour [https://stormwater.pca.state.mn.us/index.php?title=Guidance_for_amending_soils_with_rapid_or_high_infiltration_rates unless amended to slow the infiltration rate].
**soils cannot be amended to achieve an infiltration rate of 0.2 inches per hour or more, or
+
**The infiltration practice is within 1,000 feet up‐gradient, or 100 feet down‐gradient of active karst features.
**the practice cannot be relocated to an area with an infiltration rate of 0.2 inches per hour or greater.
+
**The infiltration practice receives discharges from areas with high levels of contaminants in soil or groundwater and contaminants will be mobilized by the infiltrating stormwater. [https://stormwater.pca.state.mn.us/index.php?title=Stormwater_infiltration_guidance_for_sites_with_known_or_high_potential_for_soil_or_groundwater_contamination_on_or_off-site Removal or imobilization/isolation of contaminants] may allow for infiltration.
*The infiltration practice is located in areas where soil infiltration rates are more than 8.3 inches per hour and
+
*The infiltration practice is located in the one (1) year travel time from a drinking water supply well. The area within the 1-year time of travel is also called the Emergency Response Area for a water supply well. To view shapefiles, a map, or metadata for Emergency Response Areas, [http://www.health.state.mn.us/divs/eh/water/swp/maps/ link here] and select Emergency Response Areas from the Geospatial Data Files table. Infiltration may be acceptable if the vulnerability of the DWSMA is low or very low, or if the vulnerability is moderate and a technical review indicates infiltration is acceptable.
**soils cannot be amended to slow the infiltration rate below 8.3 inches per hour or
 
**the practice cannot be relocated to an area with an infiltration rate of less than 8.3 inches per hour.
 
*The infiltration practice is within 1,000 feet up‐gradient, or 100 feet down‐gradient of active karst features and the practice cannot be relocated to achieve greater separation distances.
 
*The infiltration practice receives discharges from areas with high levels of contaminants in soil or groundwater and contaminants will be mobilized by the infiltrating stormwater.
 
*The infiltration practice is located in the one (1) year travel time from a drinking water supply well. The area within the 1-year time of travel is also called the Emergency Response Area for a water supply well. To view shapefiles, a map, or metadata for Emergency Response Areas, [http://www.health.state.mn.us/divs/eh/water/swp/maps/ link here] and select Emergency Response Areas from the Geospatial Data Files table.
 
 
*The infiltration practice is within 10 feet of a building or structure unless a [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_groundwater_mounding mounding analysis] confirms that the building or structure will not be impacted by the infiltration practice.
 
*The infiltration practice is within 10 feet of a building or structure unless a [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_groundwater_mounding mounding analysis] confirms that the building or structure will not be impacted by the infiltration practice.
 
*The infiltration practice is located within 35 feet of a [http://www.pca.state.mn.us/index.php/water/water-types-and-programs/subsurface-sewage-treatment-system-ssts/index.html septic drainfield], unless a [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_groundwater_mounding mounding analysis] confirms that the drainfield will not be impacted by the infiltration practice.
 
*The infiltration practice is located within 35 feet of a [http://www.pca.state.mn.us/index.php/water/water-types-and-programs/subsurface-sewage-treatment-system-ssts/index.html septic drainfield], unless a [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_groundwater_mounding mounding analysis] confirms that the drainfield will not be impacted by the infiltration practice.
 
*The infiltration practice is less than 200 feet from the toe of a [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_setback_%28separation%29_distances#Site_topography_and_slopes slope greater than or equal to 20 percent].
 
*The infiltration practice is less than 200 feet from the toe of a [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_setback_%28separation%29_distances#Site_topography_and_slopes slope greater than or equal to 20 percent].
 
*The infiltration practice receives discharges from a confirmed stormwater hotspot (see [http://stormwater.pca.state.mn.us/index.php/Potential_stormwater_hotspots#Determining_if_a_PSH_is_a_hotspot  guidance]) and [[Pre-treatment|pretreatment]] practices cannot be used to achieve acceptable pollutant concentrations in the runoff. There is no specific pollutant concentration that defines a stormwater hotspot and the pollutant characteristics and removal capability of the BMP must be considered in making this determination. A suggested approach is to apply the expected pollutant removal for the BMP to the expected concentration of the pollutant and compare the remaining concentration to the water quality standard (see water quality standards for [https://www.revisor.mn.gov/rules/?id=7050 surface water] and [http://www.health.state.mn.us/divs/eh/risk/rules/water/ groundwater]). For example, the drinking water standard for zinc is 2 milligrams per liter (mg/L). The concentration of zinc in runoff from an area is 6 mg/L. Expected pollutant removal rates are 65 percent for underground infiltration and 80 percent for bioinfiltration. The resulting concentrations in effluent beneath the infiltration systems are 2.1 mg/L for underground infiltration and 1.2 mg/L for bioinfiltration. Using the drinking standard as the criteria for determining the feasibility of infiltration, bioinfiltration would be acceptable and underground infiltration would not be acceptable.
 
*The infiltration practice receives discharges from a confirmed stormwater hotspot (see [http://stormwater.pca.state.mn.us/index.php/Potential_stormwater_hotspots#Determining_if_a_PSH_is_a_hotspot  guidance]) and [[Pre-treatment|pretreatment]] practices cannot be used to achieve acceptable pollutant concentrations in the runoff. There is no specific pollutant concentration that defines a stormwater hotspot and the pollutant characteristics and removal capability of the BMP must be considered in making this determination. A suggested approach is to apply the expected pollutant removal for the BMP to the expected concentration of the pollutant and compare the remaining concentration to the water quality standard (see water quality standards for [https://www.revisor.mn.gov/rules/?id=7050 surface water] and [http://www.health.state.mn.us/divs/eh/risk/rules/water/ groundwater]). For example, the drinking water standard for zinc is 2 milligrams per liter (mg/L). The concentration of zinc in runoff from an area is 6 mg/L. Expected pollutant removal rates are 65 percent for underground infiltration and 80 percent for bioinfiltration. The resulting concentrations in effluent beneath the infiltration systems are 2.1 mg/L for underground infiltration and 1.2 mg/L for bioinfiltration. Using the drinking standard as the criteria for determining the feasibility of infiltration, bioinfiltration would be acceptable and underground infiltration would not be acceptable.
*A mound forming beneath the infiltration practice will extend into the practice. The expected mound elevation can be [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_groundwater_mounding#How_to_predict_the_extent_of_a_mound  calculated using guidance in this manual].
+
*A [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_groundwater_mounding groundwater mound] forming beneath the infiltration practice will extend into the practice. The expected mound elevation can be [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_groundwater_mounding#How_to_predict_the_extent_of_a_mound  calculated using guidance in this manual].
*Presence of endangered species habitat.
 
*Presence of flood plains and flood fringes.
 
  
 
==Information needed==
 
==Information needed==
Site review is necessary to determine the feasibility of infiltrating stormwater runoff at a site. A site review includes both a review of information and field sampling. The following information may be of use in conducting a site review
+
Site review is necessary to determine if stormwater runoff can be infiltrated at a site. A site review includes both a review of information and field sampling. The following information may be of use in conducting a site review
*[http://www.usgs.gov/pubprod/aerial.html Aerial photos] and [http://nationalmap.gov/ustopo/ topographic maps]: used to determine slopes and distance to slopes, presence of surface water features, presence of sinkholes
+
*[https://earthexplorer.usgs.gov/ Aerial photos] and [https://www.usgs.gov/programs/national-geospatial-program/topographic-maps topographic maps]: used to determine slopes and distance to slopes, presence of surface water features, presence of sinkholes
 
*[http://websoilsurvey.sc.egov.usda.gov/App/HomePage.htm County soil surveys] and other soil information as available: used to determine likely soil infiltration rates, depth to saturated soil
 
*[http://websoilsurvey.sc.egov.usda.gov/App/HomePage.htm County soil surveys] and other soil information as available: used to determine likely soil infiltration rates, depth to saturated soil
 
*[http://www.dnr.state.mn.us/waters/groundwater_section/mapping/index.html County Geologic Atlas]: used to determine depth to bedrock, presence of karst, information for conducting mounding assessment
 
*[http://www.dnr.state.mn.us/waters/groundwater_section/mapping/index.html County Geologic Atlas]: used to determine depth to bedrock, presence of karst, information for conducting mounding assessment
 
*Local groundwater levels: used to determine depth to water, information for conducting mounding assessment
 
*Local groundwater levels: used to determine depth to water, information for conducting mounding assessment
*DWSMA and [http://www.health.state.mn.us/divs/eh/water/swp/whp/ Wellhead Protection] maps: used to determine location of DWSMA, travel times to drinking water supply wells
+
*DWSMA and [https://www.health.state.mn.us/communities/environment/water/swp/index.htm Wellhead Protection] maps: used to determine location of DWSMA, travel times to drinking water supply wells
*[https://msc.fema.gov/portal FEMA and local floodplain maps]: used to determine location of floodplain(s)
+
*[https://stormwater.pca.state.mn.us/index.php?title=Understanding_and_interpreting_soils_and_soil_boring_reports_for_infiltration_BMPs Soil borings]: used to confirm depth to saturated soil and bedrock, presence of contaminated soil or groundwater, presence of karst features; information collected can be used to verify soil types and [http://stormwater.pca.state.mn.us/index.php/Design_infiltration_rates infiltration rates can be determined] knowing the soil type
*Soil borings: used to confirm depth to saturated soil and bedrock, presence of contaminated soil or groundwater, presence of karst features; information collected can be used to estimate soil infiltration rate,
+
*Site survey: used to confirm presence of specific features such as buildings, structures, utilities, slopes, bedrock outcrops, septic systems, drinking water wells
*Site survey: used to confirm presence of specific features such as buildings, structures, utilities, slopes, bedrock outcrops, septic systems, drinking water wells; used to identify appropriate locations for infiltration practice(s)
 
 
*[http://www.pca.state.mn.us/index.php/data/wimn-whats-in-my-neighborhood/whats-in-my-neighborhood.html MPCA listing of potentially contaminated sites]: used to identify confirmed or likely sources of contaminated soil or groundwater
 
*[http://www.pca.state.mn.us/index.php/data/wimn-whats-in-my-neighborhood/whats-in-my-neighborhood.html MPCA listing of potentially contaminated sites]: used to identify confirmed or likely sources of contaminated soil or groundwater
*[http://dnr.wi.gov/files/pdf/pubs/am/am465.pdf Phase 1 and 2 Environmental Site Assessments] [http://www.pca.state.mn.us/index.php/water/water-types-and-programs/minnesotas-impaired-waters-and-tmdls/minnesotas-impaired-waters-and-total-maximum-daily-loads-tmdls.html TMDLs] and local [http://www.pca.state.mn.us/index.php/water/water-types-and-programs/minnesotas-impaired-waters-and-tmdls/impaired-waters-list.html water quality standards]: used to determine appropriate stormwater treatment practices and location of those practices
+
*[https://dnr.wi.gov/files/PDF/pubs/sb/sb007.pdf Phase 1 and 2 Environmental Site Assessments], [http://www.pca.state.mn.us/index.php/water/water-types-and-programs/minnesotas-impaired-waters-and-tmdls/minnesotas-impaired-waters-and-total-maximum-daily-loads-tmdls.html TMDLs] and local [http://www.pca.state.mn.us/index.php/water/water-types-and-programs/minnesotas-impaired-waters-and-tmdls/impaired-waters-list.html water quality standards]: used to determine appropriate stormwater treatment practices and location of those practices
*[http://www.bwsr.state.mn.us/wetlands/delineation/ Wetland delineations], [http://www.bwsr.state.mn.us/wetlands/mnram/ MNRAM assessments], and [http://www.dnr.state.mn.us/wetlands/types.html wetland classifications]: used to determine presence of surface water features, depth to saturated soil
+
*[https://websoilsurvey.sc.egov.usda.gov/App/HomePage.htm Soil surveys], [https://bwsr.state.mn.us/wetland-functional-assessment MNRAM assessments], and [https://www.dnr.state.mn.us/wetlands/index.html wetland classifications]: used to determine presence of surface water features, depth to saturated soil
 
*Proposed conditions, conceptual/preliminary site design
 
*Proposed conditions, conceptual/preliminary site design
 
*Local zoning and land use requirements/ordinances, including stormwater rate control requirements: used to determine prohibitions or restrictions
 
*Local zoning and land use requirements/ordinances, including stormwater rate control requirements: used to determine prohibitions or restrictions
Line 59: Line 60:
 
*Site inspection
 
*Site inspection
  
==Determining the amount of infiltration feasible at a site==
+
==Determining the amount of infiltration possible at a site==
 
The amount of infiltration that can be achieved at a site depends on the soil properties and BMP size. The size of the BMP may be impacted by separation distances that can be achieved.  Required or recommended separation distances are shown in the table below. For example, if bedrock is within 5 feet of the land surface, the BMP depth can only be 2 feet to achieve the 3 foot separation from bedrock unless the BMP is raised to achieve greater separation.
 
The amount of infiltration that can be achieved at a site depends on the soil properties and BMP size. The size of the BMP may be impacted by separation distances that can be achieved.  Required or recommended separation distances are shown in the table below. For example, if bedrock is within 5 feet of the land surface, the BMP depth can only be 2 feet to achieve the 3 foot separation from bedrock unless the BMP is raised to achieve greater separation.
  
 
{{:Summary of horizontal and vertical setback distances}}
 
{{:Summary of horizontal and vertical setback distances}}
  
[[File:schematic for example infiltration 2.jpg|thumb|300px|alt=schematic used for infiltration basin example|<font size=3>Schematic showing dimensions for an infiltration basin. The surface area is 6534 feet, the bottom area is 5600 feet, and the depth is 1 foot. Water is ponded in this BMP, resulting in a treatment volume of 6067 cubic feet.</font size>]]
+
[[File:schematic for example infiltration 2.jpg|thumb|300px|alt=schematic used for infiltration basin example|<font size=3>Schematic showing dimensions for an infiltration basin. The average cross-sectional area is 6067 square feet (surface area is 6534 feet and the bottom area is 5600 feet) and the depth is 1 foot. Water is ponded in this BMP, resulting in a treatment volume of 6067 cubic feet.</font size>]]
  
[[File:Tree trench no drain schematic for example.jpg|300 px|thumb|alt=schematic showing dimensions for calculator example|<font size=3>Schematic showing the dimensions of a tree trench system. The surface area of the system is 5600 square feet, the bottom surface area is 3230 square feet, the media depth is 4 feet, and the (porosity minus field capacity) is 0.25. The resulting treatment volume is therefore 4415 cubic feet.</font size>]]
+
[[File:Tree trench no drain schematic for example.jpg|300 px|thumb|alt=schematic showing dimensions for calculator example|<font size=3>Schematic showing the dimensions of a tree trench system. The average cross-sectional area is 4415 square feet (surface area of the system is 5600 square feet and the bottom surface area is 3230 square feet), the media depth is 4 feet, and the (porosity minus field capacity) is 0.25. The resulting treatment volume is therefore 4415 cubic feet.</font size>]]
  
 
The basic equation used to size a BMP is
 
The basic equation used to size a BMP is
Line 72: Line 73:
 
*for BMPs with ponded water <math> V = A * D </math>
 
*for BMPs with ponded water <math> V = A * D </math>
  
*for BMPs with water stored in soil or media <math> V = A * D * (n – FC) </math>
+
*for BMPs with water stored in soil or media (no ponded water) <math> V = A * D * (n – FC) </math>
  
 
Where
 
Where
:V = volume infiltrated by the BMP in 48 hours or less, in ft3;
+
:V = volume infiltrated by the BMP in 48 hours or less, in ft<sup>3</sup>;
:A = area of the BMP, in ft2;
+
:A = average cross-sectional area of the BMP, in ft<sup>2</sup>;
:D = depth of water ponded or stored in the BMP soil or media;
+
:D = depth of water ponded or stored in the BMP soil or media, in feet;
:n = the porosity of the media where runoff is retained, in ft3/ft3; and
+
:n = the porosity of the soil or media where runoff is retained, in ft<sup>3</sup>/ft<sup>3</sup>; and
:FC = the soil field capacity, in ft3/ft3.
+
:FC = the soil or media field capacity, in ft<sup>3</sup>/ft<sup>3</sup>.
  
BMPs with ponded water include bioinfiltration, infiltration trench, and infiltration basin. BMPs with water stored in the soil or media include tree trench, tree box, permeable pavement, and swale with a bioretention base.
+
BMPs with ponded water include bioinfiltration, infiltration trench, infiltration basin, and swales with check dams. BMPs with water stored in the soil or media include tree trench, tree box, permeable pavement, and swales with no check dams.
 
Specific equations for sizing can be found within [http://stormwater.pca.state.mn.us/index.php/Category:Calculating_credits  articles discussing credits for individual BMPs].
 
Specific equations for sizing can be found within [http://stormwater.pca.state.mn.us/index.php/Category:Calculating_credits  articles discussing credits for individual BMPs].
  
 
==Recommended field verification==
 
==Recommended field verification==
Borings
+
Field verification should be made for separation distances, depth to water, depth to bedrock, and presence of karst. Recommended numbers of borings and pits are [http://stormwater.pca.state.mn.us/index.php/Design_criteria_for_bioretention#Step_3:_Perform_field_verification_of_site_suitability presented in this Manual].
Distances
+
 
 
==Evaluation==
 
==Evaluation==
Mounding analysis
+
Field sampling and evaluation is recommended for determining soil properties (e.g. infiltration rate, presence of gleying and mottling). Recommended numbers of borings and pits are [http://stormwater.pca.state.mn.us/index.php/Design_criteria_for_bioretention#Step_3:_Perform_field_verification_of_site_suitability presented in this Manual].
Determining infiltration rates
+
 
==Reporting==
 
 
==Other guidance==
 
==Other guidance==
 +
Guidance for determining the potential for infiltrating stormwater has been developed for locations outside Minnesota.
  
Guidance for determining the feasibility of infiltrating stormwater has been developed for locations outside Minnesota. Examples can be found through a simple Google search on ''stormwater infiltration guidance''.
 
 
{{alert|Caution must be exercised in applying guidance from other locations to Minnesota since regulations may differ.|alert-warning}}
 
{{alert|Caution must be exercised in applying guidance from other locations to Minnesota since regulations may differ.|alert-warning}}
Two examples that may be useful are indicated below.
+
 
 +
Examples that may be useful are indicated below.
 
*Wisconsin: [http://dnr.wi.gov/topic/stormwater/documents/techstd1002.pdf Site Evaluation for Stormwater Infiltration]
 
*Wisconsin: [http://dnr.wi.gov/topic/stormwater/documents/techstd1002.pdf Site Evaluation for Stormwater Infiltration]
 
*Strategies/Guidance for Managing Stormwater: [http://ascelibrary.org/doi/abs/10.1061/40792(173)228 Infiltration vs. Surface Water Discharge.]  Clark, S., Baker, K., Lalor, M., Mikula, J., and Burkhardt, C. (2005). Impacts of Global Climate Change: pp. 1-12. doi: 10.1061/40792(173)228.
 
*Strategies/Guidance for Managing Stormwater: [http://ascelibrary.org/doi/abs/10.1061/40792(173)228 Infiltration vs. Surface Water Discharge.]  Clark, S., Baker, K., Lalor, M., Mikula, J., and Burkhardt, C. (2005). Impacts of Global Climate Change: pp. 1-12. doi: 10.1061/40792(173)228.
 +
*[https://www.iwapublishing.com/books/9781843393382/research-digest-infiltration-vs-surface-water-discharge-guidance-stormwater Research Digest: Infiltration vs. Surface Water Discharge: Guidance for Stormwater Managers]. 2010. Water Environment Research Foundation.
  
 +
In addition to the above references, the [http://stormwater.pca.state.mn.us/index.php/Overview_of_Minimal_Impact_Design_Standards_%28MIDS%29 Minimal Impact Design Standards] (MIDS) design sequence flowchart can be used to make decisions about the potential for infiltrating stormwater at a site. Although the flowchart focuses on [http://stormwater.pca.state.mn.us/index.php/Performance_goals_for_new_development,_re-development_and_linear_projects MIDS performance goals], it can be adapted to help determine if infiltration prohibitions exist at a site.
  
 +
{{alert|The MIDS flowchart was developed based on the 2013 Construction Stormwater permit and has not been updated to reflect changes made in the 2018 permit.|alert-warning}}
  
 
+
<!--Potential constraints to infiltration, with links to the [http://stormwater.pca.state.mn.us/index.php/Design_Sequence_Flowchart-Flexible_treatment_options MIDS flowchart] and other guidance in this manual, are shown below.
 
 
 
 
 
 
<!--
 
This page provides information for determining the feasibility of infiltrating stormwater at a site.
 
 
 
The [http://stormwater.pca.state.mn.us/index.php/Overview_of_Minimal_Impact_Design_Standards_%28MIDS%29 Minimal Impact Design Standards] (MIDS) design sequence flowchart can be used to make decisions about the feasibility of infiltrating stormwater at a site. Although the flowchart focuses on [http://stormwater.pca.state.mn.us/index.php/Performance_goals_for_new_development,_re-development_and_linear_projects MIDS performance goals], it can be adapted to help determine if infiltration restrictions exist at a site. Potential constraints to infiltration, with links to the [http://stormwater.pca.state.mn.us/index.php/Design_Sequence_Flowchart-Flexible_treatment_options MIDS flowchart] and other guidance in this manual, are shown below.
 
  
 
*[[MIDS design sequence flow chart - Box 7|Are there constraints due to lack of available right-of-way, off-site drainage and/or rate control requirements?]]
 
*[[MIDS design sequence flow chart - Box 7|Are there constraints due to lack of available right-of-way, off-site drainage and/or rate control requirements?]]
Line 120: Line 117:
 
*[[MIDS design sequence flow chart - Box 42|Are there very high infiltrating soils (more than 8 inches per hour)?]]
 
*[[MIDS design sequence flow chart - Box 42|Are there very high infiltrating soils (more than 8 inches per hour)?]]
 
*[[MIDS design sequence flow chart - Box 46|Are there adverse surface water hydrologic impacts from infiltration practices (e.g. impacting perched wetland)?]]
 
*[[MIDS design sequence flow chart - Box 46|Are there adverse surface water hydrologic impacts from infiltration practices (e.g. impacting perched wetland)?]]
*Also see guidance on [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_setback_%28separation%29_distances setback distances]
+
*Also see guidance on [http://stormwater.pca.state.mn.us/index.php/Stormwater_infiltration_and_setback_%28separation%29_distances setback distances]-->
 
 
In addition to the above questions, the sizing and design information in this manual can be used to determine the amount of infiltration feasible at a site. See sizing information in the various [http://stormwater.pca.state.mn.us/index.php/Category:Design_criteria design sections] of this manual. The [[MIDS calculator]] may also be used to calculate infiltration volumes based on BMP sizing information.
 
 
 
Guidance for determining the feasibility of infiltrating stormwater has been developed for locations outside Minnesota. Examples can be found through a simple Google search on ''stormwater infiltration guidance''.
 
  
{{alert|Caution must be exercised in applying guidance from other locations to Minnesota since regulations may differ.|alert-warning}}
+
==Related pages==
 +
*[[Overview of stormwater infiltration]]
 +
*[[Pre-treatment considerations for stormwater infiltration]]
 +
*[[BMPs for stormwater infiltration]]
 +
*[[Pollutant fate and transport in stormwater infiltration systems]]
 +
*[[Surface water and groundwater quality impacts from stormwater infiltration]]
 +
*[[Stormwater infiltration and groundwater mounding]]
 +
*[[Stormwater infiltration and setback (separation) distances]]
 +
*[[Karst]]
 +
*[[Shallow soils and shallow depth to bedrock]]
 +
*[[Shallow groundwater]]
 +
*[[Soils with low infiltration capacity]]
 +
*[[Potential stormwater hotspots]]
 +
*[[Stormwater and wellhead protection]]
 +
*[[Stormwater infiltration and contaminated soils and groundwater]]
 +
*[[Decision tools for stormwater infiltration]]
 +
*[[References for stormwater infiltration]]
  
Two examples that may be useful are indicated below.
+
<noinclude>
*Wisconsin: [http://dnr.wi.gov/topic/stormwater/documents/techstd1002.pdf Site Evaluation for Stormwater Infiltration]
+
[[Category:Level 2 - Technical and specific topic information/infiltration]]
*Strategies/Guidance for Managing Stormwater: [http://ascelibrary.org/doi/abs/10.1061/40792(173)228 Infiltration vs. Surface Water Discharge.]  Clark, S., Baker, K., Lalor, M., Mikula, J., and Burkhardt, C. (2005). Impacts of Global Climate Change: pp. 1-12. doi: 10.1061/40792(173)228.
+
</noinclude>
-->
 

Latest revision as of 17:06, 11 January 2023

This page provides guidance to help determine if infiltration Best Management Practices (BMPs) can be utilized at a site. Infiltration BMPs include bioinfiltration, infiltration basin, infiltration trench, underground infiltration, permeable pavement, dry swales, step pool swales, and tree trench or tree box with no underdrain. Note that some infiltration occurs in BMPs with underdrains, particularly if the underdrain is raised above the bottom of the BMP. If no infiltration is desired at a site, a liner should be used.

Infiltration is often utilized at a site to meet a regulatory requirement or a performance goal for stormwater volume. The following discussion does not specifically focus on utilizing infiltration to meet a requirement or performance goal, although there is a section that provides information for determining the amount of infiltration feasible at a site.

Warning: The Construction Stormwater General Permit states “Permittees must design and construct a permanent stormwater treatment system to treat the water quality volume if the project's ultimate development replaces vegetation and/or other pervious surfaces creating a net increase of one (1) or more acres of cumulative impervious surface. Permittees must calculate the water quality volume as one (1) inch times the net increase of impervious surfaces created by the project."

The following table can be used to determine if infiltration is prohibited or not recommended. Discussion of conditions where infiltration may be acceptable when site constraints exist is provided below.

Summary of situations where infiltration of stormwater runoff is prohibited or not recommended.
Link to this table

Condition Prohibited Not recommended Not recommended unless conditions are met1
Local rule or ordinance prohibits infiltration X
BMP is < 100 feet from drinking well in sensitive aquifer3 X
BMP is < 50 feet from drinking well in a non-sensitive aquifer3 X
BMP receives discharges from vehicle fueling and maintenance areas X
There is less than 3 of separation to bedrock or saturated soil if CGP applies2 X
BMP receives discharges from certain industrial facilities4 if CGP applies
BMP is in areas where high levels of contaminants in soil or groundwater will be mobilized by the infiltrating stormwater if CGP applies X
BMP is located in D soils if CGP applies X
BMP is 1,000 feet up-gradient or 100 feet down-gradient of active karst if CGP applies X
BMP is located within an Emergency Response Area in a DWSMA exhibiting high or very high vulnerability if CGP applies X
BMP is located within an Emergency Response Area (ERA) in a DWSMA exhibiting moderate vulnerability, or outside an ERA in a DWSMA exhibiting high or very high vulnerability if CGP applies, unless a higher engineering review indicates infiltration is acceptable X
BMP is located in soils with infiltration rate > 8.3 in/hr if CGP applies X
BMP is located within 1 year travel time of drinking supply well X
BMP located within 10 feet of building or structure X
BMP located within 35 feet of a septic system X
BMP located less than 200 feet from crest of slope that exceeds 20% X
BMP receives discharges from a confirmed stormwater hotspot X
A groundwater mound formed beneath the BMP during infiltration extends into the BMP X

1see discussion for conditions under which infiltration is acceptable.
2CGP = Construction Stormwater General Permit
3See Minnesota Rules Chapter 4725
4To determine if infiltration is allowed for a specific industrial sector or subsector, go to the list of sectors, select the sector of interest, and review section 8 for that sector (Use of Infiltration Devices and/or Industrial Stormwater Ponds for Stormwater Treatment and Disposal)

Determine if infiltration is prohibited

  • Determine if there are local ordinances or rules that prevent infiltration of stormwater runoff.
  • Determine if there are other prohibitions on infiltration. Infiltration is prohibited if any of the following conditions apply.
    • The infiltration practice (BMP) is less than 100 feet from a drinking water supply well in a sensitive aquifer or less than 50 feet from a drinking water well in a non-sensitive aquifer. (link).
    • The infiltration practice receives discharges from vehicle fueling and maintenance.
    • A Construction Stormwater General (CGP) permit is required and any of the following conditions applies.
      • There is less than three (3) feet of separation distance from the bottom of the infiltration system to the elevation of the seasonally saturated soils or the top of bedrock. (link)
      • The infiltration practice receives discharges from industrial facilities which are not authorized to infiltrate industrial stormwater under an NPDES/SDS Industrial Stormwater Permit issued by the MPCA. To determine if infiltration is allowed for a specific industrial sector or subsector, go to the list of sectors, select the sector of interest, and review section 8 for that sector (Use of Infiltration Devices and/or Industrial Stormwater Ponds for Stormwater Treatment and Disposal)
      • The infiltration practice receives discharges from areas with high levels of contaminants in soil or groundwater and contaminants will be mobilized by the infiltrating stormwater. (link)
      • The infiltration practice is located in areas of predominately Hydrologic Soil Group D (clay) soils. (link)
      • The infiltration practice is within 1,000 feet up‐gradient, or 100 feet down‐gradient of active karst features. (link)
      • The infiltration practice is in a Drinking Water Supply Management Area (DWSMA) as defined in Minn. R. 4720.5100, subp. 13., if the system will be located:
        • in an Emergency Response Area (ERA) within a DWSMA classified as having high or very high vulnerability as defined by the Minnesota Department of Health; or
        • in an ERA within a DWSMA classified as moderate vulnerability unless a regulated MS4 Permittee performed or approved a higher level of engineering review sufficient to provide a functioning treatment system and to prevent adverse impacts to groundwater; or
        • outside of an ERA within a DWSMA classified as having high or very high vulnerability, unless a regulated MS4 Permittee performed or approved a higher level of engineering review sufficient to provide a functioning treatment system and to prevent adverse impacts to groundwater. (link)
      • The infiltration practice is located in areas where soil infiltration rates are more than 8.3 inches per hour unless soils are amended to slow the infiltration rate below 8.3 inches per hour.

Determine if infiltration is not prohibited but is not recommended

If infiltration is not prohibited but any of the following conditions apply, infiltration is not recommended. In some cases, infiltration may be acceptable if the practice is modified, as described below.

  • A Construction Stormwater General (CGP) permit is not required but one or more of the following conditions applies.
    • There is less than three (3) feet of separation distance from the bottom of the infiltration practice to the elevation of the seasonally saturated soils or the top of bedrock.
    • The infiltration practice is located in areas of predominately Hydrologic Soil Group D (clay) soils. Modifications to allow some infiltration include replacing the soil with permeable media or using a raised underdrain or internal water storage (see here).
    • The infiltration practice is located in areas where soil infiltration rates are more than 8.3 inches per hour unless amended to slow the infiltration rate.
    • The infiltration practice is within 1,000 feet up‐gradient, or 100 feet down‐gradient of active karst features.
    • The infiltration practice receives discharges from areas with high levels of contaminants in soil or groundwater and contaminants will be mobilized by the infiltrating stormwater. Removal or imobilization/isolation of contaminants may allow for infiltration.
  • The infiltration practice is located in the one (1) year travel time from a drinking water supply well. The area within the 1-year time of travel is also called the Emergency Response Area for a water supply well. To view shapefiles, a map, or metadata for Emergency Response Areas, link here and select Emergency Response Areas from the Geospatial Data Files table. Infiltration may be acceptable if the vulnerability of the DWSMA is low or very low, or if the vulnerability is moderate and a technical review indicates infiltration is acceptable.
  • The infiltration practice is within 10 feet of a building or structure unless a mounding analysis confirms that the building or structure will not be impacted by the infiltration practice.
  • The infiltration practice is located within 35 feet of a septic drainfield, unless a mounding analysis confirms that the drainfield will not be impacted by the infiltration practice.
  • The infiltration practice is less than 200 feet from the toe of a slope greater than or equal to 20 percent.
  • The infiltration practice receives discharges from a confirmed stormwater hotspot (see guidance) and pretreatment practices cannot be used to achieve acceptable pollutant concentrations in the runoff. There is no specific pollutant concentration that defines a stormwater hotspot and the pollutant characteristics and removal capability of the BMP must be considered in making this determination. A suggested approach is to apply the expected pollutant removal for the BMP to the expected concentration of the pollutant and compare the remaining concentration to the water quality standard (see water quality standards for surface water and groundwater). For example, the drinking water standard for zinc is 2 milligrams per liter (mg/L). The concentration of zinc in runoff from an area is 6 mg/L. Expected pollutant removal rates are 65 percent for underground infiltration and 80 percent for bioinfiltration. The resulting concentrations in effluent beneath the infiltration systems are 2.1 mg/L for underground infiltration and 1.2 mg/L for bioinfiltration. Using the drinking standard as the criteria for determining the feasibility of infiltration, bioinfiltration would be acceptable and underground infiltration would not be acceptable.
  • A groundwater mound forming beneath the infiltration practice will extend into the practice. The expected mound elevation can be calculated using guidance in this manual.

Information needed

Site review is necessary to determine if stormwater runoff can be infiltrated at a site. A site review includes both a review of information and field sampling. The following information may be of use in conducting a site review

  • Aerial photos and topographic maps: used to determine slopes and distance to slopes, presence of surface water features, presence of sinkholes
  • County soil surveys and other soil information as available: used to determine likely soil infiltration rates, depth to saturated soil
  • County Geologic Atlas: used to determine depth to bedrock, presence of karst, information for conducting mounding assessment
  • Local groundwater levels: used to determine depth to water, information for conducting mounding assessment
  • DWSMA and Wellhead Protection maps: used to determine location of DWSMA, travel times to drinking water supply wells
  • Soil borings: used to confirm depth to saturated soil and bedrock, presence of contaminated soil or groundwater, presence of karst features; information collected can be used to verify soil types and infiltration rates can be determined knowing the soil type
  • Site survey: used to confirm presence of specific features such as buildings, structures, utilities, slopes, bedrock outcrops, septic systems, drinking water wells
  • MPCA listing of potentially contaminated sites: used to identify confirmed or likely sources of contaminated soil or groundwater
  • Phase 1 and 2 Environmental Site Assessments, TMDLs and local water quality standards: used to determine appropriate stormwater treatment practices and location of those practices
  • Soil surveys, MNRAM assessments, and wetland classifications: used to determine presence of surface water features, depth to saturated soil
  • Proposed conditions, conceptual/preliminary site design
  • Local zoning and land use requirements/ordinances, including stormwater rate control requirements: used to determine prohibitions or restrictions
  • Communication with local landowners, LGU, or others knowledgeable about the site
  • Site inspection

Determining the amount of infiltration possible at a site

The amount of infiltration that can be achieved at a site depends on the soil properties and BMP size. The size of the BMP may be impacted by separation distances that can be achieved. Required or recommended separation distances are shown in the table below. For example, if bedrock is within 5 feet of the land surface, the BMP depth can only be 2 feet to achieve the 3 foot separation from bedrock unless the BMP is raised to achieve greater separation.

Required and recommended minimum vertical and horizontal separation distances. This represents the minimum distance from the infiltration practice to the structure of concern. If the structure is above-ground, the distance is measured from the edge of the BMP to the structure. If the structure is underground, the vertical separation distance represents the distance from the point of infiltration through the bottom of the system to the structure, while the horizontal separation (often called setback) distance is the shortest distance from the edge of the system to the structure.
Link to this table

Structure Distance (feet) Requirement or recommendation Note(s)
Vertical Saturated soil 3 Requirement1
Bedrock 3 Requirement1
Horizontal Public supply well 100 for sensitive wells; 50 for others3 Requirement
Building/structure/property line2 10 Recommended
Surface water none unless local requirements exist If nearby stream is impaired for chloride, see [1]
Septic system 35 Recommended
Contaminated soil/groundwater No specific distance. Infiltration must not mobilize contaminants.
Slope 200 Recommended from toe of slope >= 20%
Karst 1000 up-gradient 100 down-gradient Requirement1 active karst

1 Required under the Construction Stormwater General Permit
2 Minimum with slopes directed away from the building
3If treating an average of 10,000 gallons per day; otherwise separation distance is 300 feet


schematic used for infiltration basin example
Schematic showing dimensions for an infiltration basin. The average cross-sectional area is 6067 square feet (surface area is 6534 feet and the bottom area is 5600 feet) and the depth is 1 foot. Water is ponded in this BMP, resulting in a treatment volume of 6067 cubic feet.
schematic showing dimensions for calculator example
Schematic showing the dimensions of a tree trench system. The average cross-sectional area is 4415 square feet (surface area of the system is 5600 square feet and the bottom surface area is 3230 square feet), the media depth is 4 feet, and the (porosity minus field capacity) is 0.25. The resulting treatment volume is therefore 4415 cubic feet.

The basic equation used to size a BMP is

  • for BMPs with ponded water \( V = A * D \)
  • for BMPs with water stored in soil or media (no ponded water) \( V = A * D * (n – FC) \)

Where

V = volume infiltrated by the BMP in 48 hours or less, in ft3;
A = average cross-sectional area of the BMP, in ft2;
D = depth of water ponded or stored in the BMP soil or media, in feet;
n = the porosity of the soil or media where runoff is retained, in ft3/ft3; and
FC = the soil or media field capacity, in ft3/ft3.

BMPs with ponded water include bioinfiltration, infiltration trench, infiltration basin, and swales with check dams. BMPs with water stored in the soil or media include tree trench, tree box, permeable pavement, and swales with no check dams. Specific equations for sizing can be found within articles discussing credits for individual BMPs.

Recommended field verification

Field verification should be made for separation distances, depth to water, depth to bedrock, and presence of karst. Recommended numbers of borings and pits are presented in this Manual.

Evaluation

Field sampling and evaluation is recommended for determining soil properties (e.g. infiltration rate, presence of gleying and mottling). Recommended numbers of borings and pits are presented in this Manual.

Other guidance

Guidance for determining the potential for infiltrating stormwater has been developed for locations outside Minnesota.

Caution: Caution must be exercised in applying guidance from other locations to Minnesota since regulations may differ.

Examples that may be useful are indicated below.

In addition to the above references, the Minimal Impact Design Standards (MIDS) design sequence flowchart can be used to make decisions about the potential for infiltrating stormwater at a site. Although the flowchart focuses on MIDS performance goals, it can be adapted to help determine if infiltration prohibitions exist at a site.

Caution: The MIDS flowchart was developed based on the 2013 Construction Stormwater permit and has not been updated to reflect changes made in the 2018 permit.


Related pages

This page was last edited on 11 January 2023, at 17:06.