Unit costs related to diversion and working in the dry

Unit costs related to diversion and working in the dry

Link to this table

Bid Item Item Description Units Average Price
2105601/00045 Temporary stream diversion system lump sum $27,523.34
2452601/00011 Steel sheet piling (temporary) lump sum $31,747.97
2452618/00011 Steel sheet piling (temporary) square foot $37.64